Provincial OHS law requires hazards to be assessed and controlled before work starts. A field level hazard assessment (FLHA) for flat roof membrane installation is done on site at the start of the shift and again whenever conditions change.

It lists the tasks, hazards and controls, and every worker signs on before starting and signs off at the end of the shift. The main hazards are falling from a roof edge, falling through a floor opening or void, falling through a fragile roof or skylight and fire from hot works.

FLHA example: flat roof membrane installation

This is a complete FLHA for flat roof membrane installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Field Level Hazard Assessment (FLHA)
Flat roof and membrane roofing · Roofing · Example
Document FLHA-001 · Rev 1

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Set up edge protection around the flat roof and guard any roof openings or skylights
  • Falling from a roof edge
  • Falling through a floor opening or void
  • Falling through a fragile roof or skylight
Critical
  • Do what you can from the ground or from a scaffold at the gutter line, for example pre-assemble parts on the ground. Elimination
  • Install edge protection or guardrails on all open roof edges before work starts. Engineering (guarding)
  • Use a perimeter scaffold with handrails and toe boards along the eaves where practical. Engineering
  • Where guardrails cannot be fitted, use fall restraint on certified roof anchors so workers cannot reach the edge. Engineering
  • Use one safe, controlled access point and keep others off the roof. Administrative
  • Cover every hole and penetration with a fixed, secured cover marked "HOLE" or "DANGER". Engineering (guarding)
  • Put guardrails with toe boards around stairwells, lift shafts, voids and open edges. Engineering (guarding)
  • Install stairs early and fit temporary handrails as soon as they go in. Engineering
  • Never remove a cover or guardrail without approval. Put it back straight away. Administrative
  • Inspect covers and barriers daily and after other trades have been through. Administrative
  • Work from underneath or from an aerial work platform so nobody stands on the fragile roof. Elimination
  • Cover or guard every skylight and fragile sheet with a fixed, marked cover or mesh before work starts. Engineering (guarding)
  • Install safety mesh under new roof sheeting, and use crawl boards or staging to spread the load on fragile surfaces. Engineering
  • Use fall arrest on rated anchors when working near fragile areas. Engineering
  • Treat all roof sheets as fragile until a competent person confirms they are not. Old fibre cement and plastic sheets are fragile. Administrative
Medium
2Lift materials up with a hoist, keeping the area below closed off
  • Falling tools and materials
  • Lifting and carrying heavy loads
  • Public entering the work area
High
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Engineering (guarding)
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Engineering
  • Use catch fans, debris netting or covered walkways where people pass below. Engineering
  • Tether hand tools when working at height. Engineering
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Administrative
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Elimination
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitution
  • Use trolleys, pallet jacks, hoists, vacuum lifters or equipment instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Engineering (guarding)
  • Give pedestrians a safe, marked path around the work, with ramps for strollers and wheelchairs. Engineering (guarding)
  • Use hoarding, covered walkways or catch fans where work is above public areas. Engineering
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Administrative
  • Make the site safe at the end of each day: cover holes, lower buckets and booms, remove ladders and lock tools away. Administrative
Medium
3Strip the old covering and check the deck for rot
  • Lifting and carrying heavy loads
  • Cuts from sharp edges
  • General dust
High
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Lifting and carrying heavy loads: see step 2 for the full controls Administrative
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Engineering
  • Use knives with retractable or self-retracting blades. Engineering
  • Cut away from your body and keep your other hand clear. Administrative
  • Put used blades in a blade bin or sharps container. Administrative
  • Use two people to handle large sheets of metal or glass. Administrative
  • Use low-dust products, such as dust-reduced or pre-mixed compounds. Substitution
  • Seal off the work area with plastic sheeting in occupied buildings. Engineering (guarding)
  • Use tools with dust extraction and a vacuum for clean up. Engineering
  • Lightly mist the area with water to keep dust down, away from anything electrical. Engineering
  • Never dry sweep or blow dust off with compressed air. Administrative
Medium
4Apply primers and adhesives with good airflow and away from flames
  • Hazardous chemicals
  • Flammable liquids and gases
High
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitution
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Read the Safety Data Sheet (SDS) and WHMIS labels before use. Workers have WHMIS training. Administrative
  • Keep chemicals in labelled containers. Never decant into drink bottles. Administrative
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Administrative
  • Have eye wash and a spill kit nearby, and wash hands before eating. Administrative
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
  • Use non-flammable or water-based products where you can. Substitution
  • Keep ignition sources away: no smoking, no hot work and no running engines near flammables. Engineering (guarding)
  • Store fuels and solvents in approved, closed containers in a ventilated area away from the work. Engineering
  • Refuel equipment outdoors with the engine off and cool. Administrative
  • Keep only what you need for the day on site. Administrative
  • Store gas cylinders upright, secured and outdoors. Administrative
  • Keep a suitable fire extinguisher where flammables are used or stored. Administrative
  • Wear chemical gloves and safety glasses when pouring or mixing. PPE
Medium
5Torch on membrane under a hot work permit, with an extinguisher and a fire watch after
  • Fire from hot works
  • Burns from hot surfaces
  • Fire and emergencies
Critical
  • Use cold work methods where you can, such as bolting, press fittings or cutting with a saw instead of a torch. Elimination
  • Move anything that can burn at least 10 metres away, or cover it with fire blankets. Engineering (guarding)
  • Use fire-resistant screens to stop sparks reaching people or gaps in walls and floors. Engineering
  • Get a hot work permit before starting. Administrative
  • Keep a charged fire extinguisher and fire blanket at the work spot. Administrative
  • Isolate heating systems and let parts cool before you touch them. Elimination
  • Fit guards or insulation on hot pipes and equipment. Engineering
  • Mark hot items with chalk or a "HOT" sign so others know. Administrative
  • Keep a first aid kit and cool running water nearby for burns. Administrative
  • Wear heat-resistant gloves and long sleeves. PPE
  • Provide fire extinguishers suited to the site, checked and easy to reach. Engineering
  • Keep exits and escape routes clear and signed. Engineering
  • Have a site emergency plan: alarm, exits, assembly point and emergency contacts. Administrative
  • Keep a stocked first aid kit and at least one trained first aider on site. Administrative
  • Know the site address and how emergency services get in. Call 911. Administrative
Medium
6Seal outlets and edges, clear the roof and remove access
  • Poor housekeeping and waste
  • Heat stress
  • Sun exposure (UV)
High
  • Order materials to size and send packaging back where you can. Elimination
  • Put waste bins and chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Schedule heavy work for the cooler part of the day. Elimination
  • Provide shade over work and rest areas, and fans or cooling in attics. Engineering
  • Supply cool drinking water close by and drink a cup every 15 to 20 minutes. Administrative
  • Take regular rest breaks in the shade, more often as it gets hotter. Administrative
  • Let new and returning workers build up to full work in the heat over about a week. Administrative
  • Plan outdoor work for early morning or late afternoon when UV is lower. Elimination
  • Put shade covers over fixed work areas. Engineering
  • Check the UV index each day. Use sun protection when it is 3 or higher. Administrative
  • Check your skin regularly and see a doctor about any new or changing spots. Administrative
  • Wear a broad-brim hat or hard hat brim, long sleeves, sunglasses and SPF 30 or higher sunscreen, reapplied every 2 hours. PPE
Medium

PPE

CSA green triangle safety boots (CSA Z195)Full body harness (fall arrest)Work glovesSafety glasses (CSA Z94.3)Respirator fit tested to CSA Z94.4 (P100 for dust, or the type the air test calls for)Sun protection (sunscreen, hat, long sleeves)Hard hat (CSA Z94.1)High-visibility vest (CSA Z96)Cut-resistant glovesN95 respiratorChemical-resistant glovesSafety gogglesCoverallsWelding glovesFace shield

Plant and equipment

Propane torchHand toolsExtension ladderMaterial hoist

Permits and plans

Roof access permitFall protection planHot work permit

Emergency

Call 911. Add the nearest hospital, the muster point and the first aid attendant for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this FLHA, then sign off at the end of the shift.

Free FLHA template for flat roof membrane installation

Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this FLHA

Pre-start checklist for flat roof membrane installation

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Set up edge protection around the flat roof and guard any roof openings or skylights
  2. Lift materials up with a hoist, keeping the area below closed off
  3. Strip the old covering and check the deck for rot
  4. Apply primers and adhesives with good airflow and away from flames
  5. Torch on membrane under a hot work permit, with an extinguisher and a fire watch after
  6. Seal outlets and edges, clear the roof and remove access

Hazards to watch on flat roof membrane installation

The hazards most specific to this job, and the step where each one comes up.

Step 1Falling through a fragile roof or skylightA worker steps on a skylight, clear sheet or old fibre cement roof and falls through to the floor below.
Step 5Burns from hot surfacesTouching hot pipes, tools, bitumen, solder or freshly welded metal burns the skin.
Step 4Flammable liquids and gasesGasoline, solvents, thinners and propane catch fire or explode when vapour reaches a spark, flame or hot surface.
Step 5Fire and emergenciesA fire, injury or other emergency happens and workers cannot get out, raise the alarm or get first aid in time.
Step 6Sun exposure (UV)Long hours in the sun cause sunburn, eye damage and skin cancer.
Step 5Fire from hot worksSparks and heat from welding, grinding or flame torches set fire to timber, insulation, rubbish or fuel nearby.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: First aid only to FatalityBA
Highest risk on flat roof membrane installation: Critical before controls (B), down to Medium after controls (A), on the Canada 5 by 5 risk matrix (likely and fatality becomes unlikely and serious injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Could anyone fall 3 metres or more, or fall any distance into machinery, water, a hazardous substance or through an opening?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Will you use a scaffold or mobile tower?
  • Will you use an aerial work platform (scissor lift or boom lift)?

Why FLHAs get rejected

Prime contractors and COR auditors send documents back for these reasons. This example avoids them, but check yours too.

  • End of shift boxes already say "None" when the form was signed at the start of the shift.
  • One FLHA reused for days or weeks, or a "review by" date a month away, when the work and conditions change daily.
  • No time of assessment and no record of any revision, which Alberta s.7(3) requires.
  • Workers signed that they "read" it, but nothing shows they took part, which Alberta s.8(1) requires.
  • Work at height with no fall protection plan where the province requires one, or no written rescue procedure for workers using fall arrest.
  • Permits or locates required on site but no permit or ticket numbers recorded.
  • No re-assessment entry after an obvious change such as weather, a new task or a new crew member.

Rules by province for flat roof membrane installation

Province or territoryKey local ruleRegulator
OntarioFall protection (O. Reg. 213/91 s.26) applies at a fall of more than 3 m, more than 1.2 m where the work area is used as a path for a wheelbarrow or similar equipment, and at any height into operating machinery, water or other liquid, a hazardous substance, or through an opening.Ontario Ministry of Labour, Immigration, Training and Skills Development
British ColumbiaFall protection is required where a fall of 3 m or more may occur (s.11.2). A written fall protection plan is required at 7.5 m or more where there are no permanent guardrails (s.11.3).WorkSafeBC
AlbertaA hazard assessment must be done before work begins, and before a new work site is built (OHS Code s.7(1)). The results must be written down with the controls (s.7(2)).Alberta Occupational Health and Safety
QuebecGuardrails (Safety Code s.2.9.1, as amended by Decret 63-2025) are needed where a worker could fall into liquid or a hazardous substance, onto moving parts or dangerous equipment, 1.2 m or more when using a vehicle, 1.5 m or more when handling a load, and more than 3 m in all other cases.CNESST (Commission des normes, de l'equite, de la sante et de la securite du travail)
ManitobaA prime contractor is required whenever more than one employer or self employed person works on the site at the same time (Act s.7).Manitoba Workplace Safety and Health Branch
SaskatchewanAn occupational health committee is required at 10 or more workers of one employer (Act s.3-22).Saskatchewan Ministry of Labour Relations and Workplace Safety, OHS Division
Nova ScotiaWorkers must be trained in fall protection before using it or working in, supervising or planning work in a fall protection area, with a refresher at least every 3 years (WHSR s.21.19).Nova Scotia Department of Labour, Skills and Immigration, Safety Branch (OHS)
New BrunswickFall protection is needed from 3 m above water or the nearest permanent safe level (Reg 91-191 s.49(1)(a)(i)).WorkSafeNB
Newfoundland and LabradorGive written notice to the minister before starting a construction project that will last 30 days or more, with the site, location, type of work and number of workers (Regs s.8).Government Services, Occupational Health and Safety Division
Prince Edward IslandFall protection is needed from 3 m above the nearest safe surface or water (Fall Protection Regulations s.2(1)(a)).Workers Compensation Board of PEI, OHS Division
YukonEvery employer must do hazard assessments with the committee, representative or workers, and redo them after significant changes or incidents (Regs s.1.03.01).Yukon Workers' Safety and Compensation Board
Northwest TerritoriesFall protection is needed from 3 m, or lower if there is a risk of injury (s.119(1)). Guardrails are needed for falls of 1.2 m to 3 m at permanent work sites (s.119(2)).Workers' Safety and Compensation Commission (WSCC)
NunavutNo 911. To reach the RCMP in an emergency, dial your community's first three digits then 1111 (Iqaluit: 979-1111). Put the local fire, ambulance and RCMP numbers on every FLHA.Workers' Safety and Compensation Commission (WSCC)

Questions

Do I need an FLHA for flat roof membrane installation?

Provincial OHS law requires hazards to be assessed and controlled before work starts. A field level hazard assessment (FLHA) for flat roof membrane installation is done on site at the start of the shift and again whenever conditions change.

Who signs the FLHA?

The supervisor and every worker take part in the assessment and sign on before work starts, then sign off at the end of the shift. Review it and re-sign whenever the task or conditions change.

How long do I keep it?

Keep completed hazard assessments for at least 3 years (COR auditors sample the last 12 months). Review this FLHA and re-sign whenever the task, crew or conditions change.

What PPE is needed for flat roof membrane installation?

Usually CSA green triangle safety boots (CSA Z195), Full body harness (fall arrest), Work gloves, Safety glasses (CSA Z94.3), Respirator fit tested to CSA Z94.4 (P100 for dust, or the type the air test calls for), Sun protection (sunscreen, hat, long sleeves), Hard hat (CSA Z94.1), High-visibility vest (CSA Z96), Cut-resistant gloves, N95 respirator, Chemical-resistant gloves, Safety goggles, Coveralls, Welding gloves, Face shield. The site rules may add more, so check with the general contractor.

More roofing FLHAs

Related jobs in other trades

Toolbox talks for this job

Blank FLHA template: free FLHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · United States (JHA)

Sources