Method statement for concrete driveway
You must assess the risks of concrete driveway and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, road traffic, hitting underground services and being hit by mobile plant.
RAMS example: concrete driveway
This is a complete RAMS for concrete driveway, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Set up traffic and pedestrian control at the street |
| Workers, Road users, Public, Children | Very high (15) |
| Medium (5) |
| 2 | Locate services, then excavate and level the base with the skid steer |
| Workers, Public, Visitors | Very high (15) |
| Medium (5) |
| 3 | Compact base, set forms and rebar |
| Workers, People nearby | High (12) |
| Medium (6) |
| 4 | Pour and finish the concrete |
| Workers | High (12) |
| Medium (8) |
| 5 | Saw cut control joints with water suppression |
| Workers, People nearby | Very high (20) |
| Medium (8) |
| 6 | Clean up, wash out away from drains and barricade until cured |
| Workers, Visitors, Public, Children | High (12) |
| Low (4) |
Method statement: sequence of work
- Set up traffic and pedestrian control at the street
- Locate services, then excavate and level the base with the skid steer
- Compact base, set forms and rebar
- Pour and finish the concrete
- Saw cut control joints with water suppression
- Clean up, wash out away from drains and barricade until cured
PPE
Plant and equipment
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for concrete driveway
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for concrete driveway
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Utility plans checked and area scanned with CAT and Genny
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone and spotter set up for plant and traffic
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, hi-vis vest, chemical-resistant gloves, safety glasses
The safe sequence of work
- Set up traffic and pedestrian control at the street
- Locate services, then excavate and level the base with the skid steer
- Compact base, set forms and rebar
- Pour and finish the concrete
- Saw cut control joints with water suppression
- Clean up, wash out away from drains and barricade until cured
Hazards to watch on concrete driveway
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Skid steer loader: CPCS or NPORS skid steer card
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Safety at Street Works and Road Works Code of Practice (Red Book); CDM Regulations 2015; HSE HSG47 Avoiding danger from underground services; CDM Regulations 2015 and PUWER 1998; Control of Vibration at Work Regulations 2005; Control of Noise at Work Regulations 2005; Manual Handling Operations Regulations 1992; COSHH Regulations 2002; Provision and Use of Work Equipment Regulations 1998 (PUWER).
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for concrete driveway?
You must assess the risks of concrete driveway and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for concrete driveway?
Usually Safety boots, Hi-vis vest, Chemical-resistant gloves, Safety glasses, Ear defenders, Sun protection (sunscreen and neck cover), Safety helmet, Rigger gloves, Safety goggles, Knee pads, Half-mask respirator (P3 filters), FFP3 dust mask. The site rules may add more, so check with the principal contractor.