Method statement for re-roofing
You must assess the risks of re-roofing and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, falling from height, disturbing asbestos and scaffold collapse or fall from scaffold.
RAMS example: re-roofing
This is a complete RAMS for re-roofing, with 11 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the asbestos survey and get any asbestos roof removed first, by an HSE licensed asbestos contractor where the work is licensable |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 2 | Check the weather and power lines, and plan the crane, hoist and skip positions |
| Workers, Plant operators, Public | High (12) |
| Medium (5) |
| 3 | Erect full perimeter scaffold edge protection, a waste chute and an exclusion zone below |
| Workers, People below, Public, Children | Very high (20) |
| Medium (8) |
| 4 | Strip the old roof in sections so the building stays covered if rain comes |
| Workers, Public, People below | Very high (15) |
| Medium (6) |
| 5 | Lower waste in the chute or by crane, never throw it off |
| Workers, Public, People below, Visitors | High (12) |
| Medium (8) |
| 6 | Check and repair the roof framing, guarding any gaps |
| Workers, Occupants, People below | Very high (20) |
| Medium (5) |
| 7 | Fit the roofing underlay and battens, with safety nets or a boarded platform under any open roof where someone could fall through |
| Workers, People below | Very high (20) |
| Medium (6) |
| 8 | Land new roofing materials by crane or hoist, spreading loads across the frame |
| Workers, Public, Occupants | High (10) |
| Medium (5) |
| 9 | Lay the new roof, taking breaks in heat and sun |
| Workers | High (12) |
| Medium (8) |
| 10 | Fit flashings, ridge tiles, gutters and downpipes |
| Workers, People nearby | High (12) |
| Medium (8) |
| 11 | Clean the roof and site, then dismantle scaffold once the roof is signed off |
| Workers, Visitors, Public, People below | Very high (15) |
| Medium (5) |
Method statement: sequence of work
- Check the asbestos survey and get any asbestos roof removed first, by an HSE licensed asbestos contractor where the work is licensable
- Check the weather and power lines, and plan the crane, hoist and skip positions
- Erect full perimeter scaffold edge protection, a waste chute and an exclusion zone below
- Strip the old roof in sections so the building stays covered if rain comes
- Lower waste in the chute or by crane, never throw it off
- Check and repair the roof framing, guarding any gaps
- Fit the roofing underlay and battens, with safety nets or a boarded platform under any open roof where someone could fall through
- Land new roofing materials by crane or hoist, spreading loads across the frame
- Lay the new roof, taking breaks in heat and sun
- Fit flashings, ridge tiles, gutters and downpipes
- Clean the roof and site, then dismantle scaffold once the roof is signed off
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for re-roofing
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Fragile roof areas and skylights covered or barricaded
- Scaffold inspected in the last 7 days, tag in date
- Overhead lines identified and safe distances marked
- Asbestos register or survey checked for the work area
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, full body harness and lanyard, safety helmet, cut-resistant gloves
The safe sequence of work
- Check the asbestos survey and get any asbestos roof removed first, by an HSE licensed asbestos contractor where the work is licensable
- Check the weather and power lines, and plan the crane, hoist and skip positions
- Erect full perimeter scaffold edge protection, a waste chute and an exclusion zone below
- Strip the old roof in sections so the building stays covered if rain comes
- Lower waste in the chute or by crane, never throw it off
- Check and repair the roof framing, guarding any gaps
- Fit the roofing underlay and battens, with safety nets or a boarded platform under any open roof where someone could fall through
- Land new roofing materials by crane or hoist, spreading loads across the frame
- Lay the new roof, taking breaks in heat and sun
- Fit flashings, ridge tiles, gutters and downpipes
- Clean the roof and site, then dismantle scaffold once the roof is signed off
Hazards to watch on re-roofing
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone use a ladder or stepladder?
- Will you use a MEWP (scissor lift or cherry picker)?
- Will you sand, scrape, burn off or cut old paint in a building from before 1992?
- Will you cut, grind or drill concrete, brick, stone, tiles or fibre cement?
- Will you use chemicals, solvents, glues, paints or fuels?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle
- Mobile crane: CPCS or NPORS crane operator card, plus slinger signaller card; lift plan by an Appointed Person
- Telehandler: CPCS or NPORS telehandler card
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Control of Asbestos Regulations 2012; HSE GS6 Avoiding danger from overhead power lines; Lifting Operations and Lifting Equipment Regulations 1998 (LOLER); Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 10 (falling objects); CDM Regulations 2015; Work at Height Regulations 2005, regulation 9 (fragile surfaces); Manual Handling Operations Regulations 1992; CDM Regulations 2015, regulation 19 (stability of structures); Provision and Use of Work Equipment Regulations 1998 (PUWER).
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for re-roofing?
You must assess the risks of re-roofing and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for re-roofing?
Usually Safety boots, Full body harness and lanyard, Safety helmet, Cut-resistant gloves, Safety glasses, FFP3 dust mask, Ear defenders, Sun protection (sunscreen and neck cover), Half-mask respirator (P3 filters), Coveralls, Rigger gloves, Hi-vis vest, Face shield. The site rules may add more, so check with the principal contractor.