Method statement for structural steel erection
You must assess the risks of structural steel erection and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, welding and cutting fumes, MEWP tip-over or crush and fire from hot works.
RAMS example: structural steel erection
This is a complete RAMS for structural steel erection, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Review the erection sequence and lift plan, and check the crane sits on firm ground |
| Workers, Public, Occupants | High (10) |
| Medium (5) |
| 2 | Check for power lines and set the exclusion zone |
| Workers, Plant operators, Public, Children, People below | High (12) |
| Medium (8) |
| 3 | Check holding down bolts and footings are ready before steel arrives |
| Workers, Occupants | High (10) |
| Medium (5) |
| 4 | Sling and lift members with a slinger signaller |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 5 | Guide members into place with tag lines, never standing under the load, and line up bolt holes with a podger, never fingers |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 6 | Bolt connections from the MEWP, clipped on |
| Workers, People nearby, People below | Very high (20) |
| Medium (5) |
| 7 | Install temporary bracing or guying to the erection design before releasing the crane from each member, and leave it until the permanent bracing is complete |
| Workers, Occupants, Public | High (12) |
| Medium (5) |
| 8 | Plumb the frame, then tension bolts or weld under a hot work permit |
| Workers, People nearby, Occupants, Public | Very high (16) |
| Medium (8) |
| 9 | Check connections and permanent bracing, then clean up offcuts and bolts |
| Workers, Visitors, Public, People below | High (12) |
| Medium (8) |
Method statement: sequence of work
- Review the erection sequence and lift plan, and check the crane sits on firm ground
- Check for power lines and set the exclusion zone
- Check holding down bolts and footings are ready before steel arrives
- Sling and lift members with a slinger signaller
- Guide members into place with tag lines, never standing under the load, and line up bolt holes with a podger, never fingers
- Bolt connections from the MEWP, clipped on
- Install temporary bracing or guying to the erection design before releasing the crane from each member, and leave it until the permanent bracing is complete
- Plumb the frame, then tension bolts or weld under a hot work permit
- Check connections and permanent bracing, then clean up offcuts and bolts
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for structural steel erection
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for structural steel erection
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- MEWP pre-use check done and the operator holds an IPAF card
- Overhead lines identified and safe distances marked
- Hot work permit issued, extinguisher at hand, fire watch arranged
- Exclusion zone below the work and public kept out
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety helmet, hi-vis vest, full body harness and lanyard
The safe sequence of work
- Review the erection sequence and lift plan, and check the crane sits on firm ground
- Check for power lines and set the exclusion zone
- Check holding down bolts and footings are ready before steel arrives
- Sling and lift members with a slinger signaller
- Guide members into place with tag lines, never standing under the load, and line up bolt holes with a podger, never fingers
- Bolt connections from the MEWP, clipped on
- Install temporary bracing or guying to the erection design before releasing the crane from each member, and leave it until the permanent bracing is complete
- Plumb the frame, then tension bolts or weld under a hot work permit
- Check connections and permanent bracing, then clean up offcuts and bolts
Hazards to watch on structural steel erection
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
- Was the building built before 2000?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Mobile crane: CPCS or NPORS crane operator card, plus slinger signaller card; lift plan by an Appointed Person
- Boom MEWP: IPAF PAL card (3b)
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Lifting Operations and Lifting Equipment Regulations 1998 (LOLER); CDM Regulations 2015, regulation 19 (stability of structures); HSE GS6 Avoiding danger from overhead power lines; CDM Regulations 2015; Work at Height Regulations 2005, regulation 10 (falling objects); Work at Height Regulations 2005 and LOLER 1998; Work at Height Regulations 2005; COSHH Regulations 2002; CDM 2015 regs 29 to 31 (fire on construction sites). Occupied premises: Regulatory Reform (Fire Safety) Order 2005 (England and Wales), Fire (Scotland) Act 2005, Fire Safety Regulations (NI) 2010.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for structural steel erection?
You must assess the risks of structural steel erection and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for structural steel erection?
Usually Safety boots, Safety helmet, Hi-vis vest, Full body harness and lanyard, Rigger gloves, Safety glasses, Welding helmet, Welding gauntlets, Half-mask respirator (P3 filters), Coveralls, Face shield, Safety goggles. The site rules may add more, so check with the principal contractor.