Method statement for internal door hanging

You must assess the risks of internal door hanging and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are lead paint dust and fumes, lifting and carrying heavy loads, saw cuts and kickback and wood and MDF dust.

RAMS example: internal door hanging

This is a complete RAMS for internal door hanging, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Hang doors and fit hardware · Carpentry · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Set up a work area away from occupants and walkways
  • Working in an occupied home or building
  • Slips and trips
Residents, Children, Staff, Workers, Visitors, PublicMedium (9)
  • Plan noisy, dusty or risky work for when the building is empty. Eliminate
  • Close off the work area with barriers, plastic sheeting or locked doors, and put up signs. Isolate
  • Keep fire exits and paths clear at all times. Control (procedures)
  • Tell occupants before you turn off power, water or gas, and before noisy or dusty work. Control (procedures)
  • Lock away tools, chemicals and materials each day, out of reach of children. Control (procedures)
  • Clean up dust and debris at the end of each day. Control (procedures)
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Fill or cover holes, and lay boards or mats on muddy access paths. Control (engineering)
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Control (procedures)
  • Keep work areas, stairs and access paths well lit. Control (procedures)
  • Wear safety boots with good grip, laced up. PPE
Low (4)
2Remove old doors and frames, checking old paint for lead
  • Lead paint dust and fumes
  • Lifting and carrying heavy loads
Workers, Residents, ChildrenHigh (12)
  • Test old paint for lead before you sand, scrape, cut or heat it. Eliminate
  • Use wet scraping, chemical strippers or shrouded tools with extraction instead of dry sanding. Never burn off lead paint with an open flame. Reduce / substitute
  • Seal off the work area with plastic sheeting and keep residents, children and pets out. Isolate
  • Clean up with an H-class vacuum and wet wipes. Never dry sweep. Control (engineering)
  • Wash hands and face before eating, drinking or smoking. Change out of dusty clothes before going home. Control (procedures)
  • Wear an FFP3 mask, disposable coveralls and gloves. PPE
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Lifting and carrying heavy loads: see step 4 for the full controls Control (procedures)
Medium (6)
3Trim doors to size and rout hinges with dust extraction
  • Saw cuts and kickback
  • Wood and MDF dust
  • Injury from power tools
  • Loud noise
Workers, People nearbyHigh (12)
  • Keep blade guards fitted and working, and use the riving knife on table saws. Control (engineering)
  • Use push sticks and clamps, and support long pieces so they do not pinch the blade. Control (engineering)
  • Use a sharp, undamaged blade made for the material. Control (procedures)
  • Stand to one side of the blade line, out of the kickback path. Control (procedures)
  • Buy pre-cut or pre-finished timber where you can. Reduce / substitute
  • Cut outdoors or in a well-ventilated area away from others. Isolate
  • Use saws and sanders with dust extraction connected to an M-class (or better) vacuum. Control (engineering)
  • Clean up with a vacuum, not a broom or compressed air. Control (procedures)
  • Do a COSHH assessment for hardwood and MDF dust. Control (procedures)
  • Keep all guards fitted and working. Never tie back or remove a guard. Control (engineering)
  • Clamp or secure the work piece. Do not hold it by hand. Control (engineering)
  • Only trained, competent people use power tools, following the maker's instructions. Control (procedures)
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Control (procedures)
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Reduce / substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Control (engineering)
  • Limit time on noisy tools and rotate workers. Control (procedures)
  • Assess noise. At 85 dB(A) or more, hearing protection is required and the zone must be marked. Control (procedures)
Medium (8)
4Hang the door with help, as solid and fire doors are heavy
  • Lifting and carrying heavy loads
  • Repetitive work and awkward postures
WorkersHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Use tools that cut the effort: powered screwdrivers, long-handled tools and extension poles for overhead work. Reduce / substitute
  • Set work up at waist height on benches or trestles where you can. Control (engineering)
  • Use light tools with good grips, and keep blades and bits sharp. Control (engineering)
  • Rotate tasks and take short breaks every hour on repetitive work. Control (procedures)
  • Warm up before heavy physical work and report aches and pains early. Control (procedures)
  • Wear knee pads for kneeling work and gloves for grip. PPE
Medium (6)
5Fit locks and closers, test operation and clean up
  • Injury from power tools
  • Poor housekeeping and waste
Workers, People nearby, VisitorsMedium (9)
  • No loose clothing, jewellery or long hair near spinning parts. Control (procedures)
  • Wear safety glasses and hearing protection. Do not wear loose gloves on drills or other rotating tools. PPE
  • Injury from power tools: see step 3 for the full controls Control (procedures)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Medium (6)

Method statement: sequence of work

  1. Set up a work area away from occupants and walkways
  2. Remove old doors and frames, checking old paint for lead
  3. Trim doors to size and rout hinges with dust extraction
  4. Hang the door with help, as solid and fire doors are heavy
  5. Fit locks and closers, test operation and clean up

PPE

Safety bootsSafety glassesFFP3 dust maskEar defendersHalf-mask respirator (P3 filters)CoverallsRigger glovesKnee pads

Plant and equipment

Power drillRouterCircular sawHand tools

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for internal door hanging

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for internal door hanging

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Set up a work area away from occupants and walkways
  2. Remove old doors and frames, checking old paint for lead
  3. Trim doors to size and rout hinges with dust extraction
  4. Hang the door with help, as solid and fire doors are heavy
  5. Fit locks and closers, test operation and clean up

Hazards to watch on internal door hanging

The hazards most specific to this job, and the step where each one comes up.

Step 3Wood and MDF dustSawing and sanding timber, MDF and treated wood makes fine dust that causes asthma, skin problems and some cancers.
Step 2Lead paint dust and fumesLead paint was common before the 1970s and was used in some buildings until 1992. Sanding, scraping or heating it releases dust or fumes that poison workers and families, especially children.
Step 1Working in an occupied home or buildingResidents, staff or children wander into the work area and get hurt, or the work blocks exits or cuts off power or water while people are inside.
Step 3Saw cuts and kickbackCircular saws, drop saws and table saws cut fingers and hands or throw material back at the user.
Step 3, 5Injury from power toolsDrills, saws, routers and sanders kick back, catch clothing or throw debris, causing cuts, broken bones and eye injuries.
Step 4Repetitive work and awkward posturesDoing the same movement for hours, kneeling or working overhead causes long-term damage to joints, muscles and tendons.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on internal door hanging: High before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (possible and major injury becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for internal door hanging?

You must assess the risks of internal door hanging and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for internal door hanging?

Usually Safety boots, Safety glasses, FFP3 dust mask, Ear defenders, Half-mask respirator (P3 filters), Coveralls, Rigger gloves, Knee pads. The site rules may add more, so check with the principal contractor.