Method statement for roof truss installation
You must assess the risks of roof truss installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, falling from height, scaffold collapse or fall from scaffold and falling through a floor opening or void.
RAMS example: roof truss installation
This is a complete RAMS for roof truss installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Erect perimeter scaffold or edge protection at roof height before trusses go up |
| Workers, People below, Public | Very high (20) |
| Medium (5) |
| 2 | Lift trusses by crane with a slinger signaller, keeping everyone clear of the load |
| Workers, Public, People below, Plant operators | High (12) |
| Medium (8) |
| 3 | Fix trusses from a stable platform, not by walking the top plates |
| Workers, People below, Visitors | Very high (20) |
| Medium (5) |
| 4 | Install temporary bracing as each truss goes in |
| Workers, Occupants, Public | High (12) |
| Medium (5) |
| 5 | Fix tie-downs and permanent bracing with nail guns |
| Workers, People nearby | High (12) |
| Medium (8) |
| 6 | Clear offcuts and check bracing before handing over to the roofer |
| Workers, Visitors, Public, People below | High (12) |
| Medium (8) |
Method statement: sequence of work
- Erect perimeter scaffold or edge protection at roof height before trusses go up
- Lift trusses by crane with a slinger signaller, keeping everyone clear of the load
- Fix trusses from a stable platform, not by walking the top plates
- Install temporary bracing as each truss goes in
- Fix tie-downs and permanent bracing with nail guns
- Clear offcuts and check bracing before handing over to the roofer
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for roof truss installation
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for roof truss installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Openings, voids and penetrations covered and marked
- Scaffold inspected in the last 7 days, tag in date
- Overhead lines identified and safe distances marked
- Exclusion zone below the work and public kept out
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, full body harness and lanyard, safety helmet, safety glasses
The safe sequence of work
- Erect perimeter scaffold or edge protection at roof height before trusses go up
- Lift trusses by crane with a slinger signaller, keeping everyone clear of the load
- Fix trusses from a stable platform, not by walking the top plates
- Install temporary bracing as each truss goes in
- Fix tie-downs and permanent bracing with nail guns
- Clear offcuts and check bracing before handing over to the roofer
Hazards to watch on roof truss installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a MEWP (scissor lift or cherry picker)?
- Was the building built before 2000?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Mobile crane: CPCS or NPORS crane operator card, plus slinger signaller card; lift plan by an Appointed Person
- Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Work at Height Regulations 2005; Lifting Operations and Lifting Equipment Regulations 1998 (LOLER); Work at Height Regulations 2005, regulation 10 (falling objects); HSE GS6 Avoiding danger from overhead power lines; CDM Regulations 2015, regulation 19 (stability of structures); Control of Noise at Work Regulations 2005.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for roof truss installation?
You must assess the risks of roof truss installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for roof truss installation?
Usually Safety boots, Full body harness and lanyard, Safety helmet, Safety glasses, Ear defenders, Rigger gloves, Hi-vis vest, Sun protection (sunscreen and neck cover), Safety goggles, Face shield. The site rules may add more, so check with the principal contractor.