Method statement for chimney breast removal
You must assess the risks of chimney breast removal and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, silica dust from concrete, brick, stone and tiles, disturbing asbestos and scaffold collapse or fall from scaffold.
RAMS example: chimney breast removal
This is a complete RAMS for chimney breast removal, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check flues for asbestos and soot, and isolate any gas appliance |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 2 | Erect scaffold around the chimney with debris protection |
| Workers, People below, Public | Very high (20) |
| Medium (8) |
| 3 | Remove bricks by hand from the top down, never undermine |
| Workers, Occupants, Public, Neighbours | Very high (15) |
| Medium (6) |
| 4 | Lower bricks by chute or hoist, keeping the area below closed |
| Workers, Public, People below, Children | High (12) |
| Medium (8) |
| 5 | Patch the roof the same day to keep weather out |
| Workers, Public, People below | Very high (20) |
| Medium (5) |
| 6 | Clean up dust and debris |
| Workers, People nearby, Visitors | Very high (20) |
| Medium (5) |
Method statement: sequence of work
- Check flues for asbestos and soot, and isolate any gas appliance
- Erect scaffold around the chimney with debris protection
- Remove bricks by hand from the top down, never undermine
- Lower bricks by chute or hoist, keeping the area below closed
- Patch the roof the same day to keep weather out
- Clean up dust and debris
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for chimney breast removal
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for chimney breast removal
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Scaffold inspected in the last 7 days, tag in date
- Asbestos register or survey checked for the work area
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone below the work and public kept out
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety helmet, full body harness and lanyard, FFP3 dust mask
The safe sequence of work
- Check flues for asbestos and soot, and isolate any gas appliance
- Erect scaffold around the chimney with debris protection
- Remove bricks by hand from the top down, never undermine
- Lower bricks by chute or hoist, keeping the area below closed
- Patch the roof the same day to keep weather out
- Clean up dust and debris
Hazards to watch on chimney breast removal
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Control of Asbestos Regulations 2012; Gas Safety (Installation and Use) Regulations 1998; Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 10 (falling objects); CDM Regulations 2015, regulation 19 (stability of structures); CDM Regulations 2015, regulation 20 (demolition); Manual Handling Operations Regulations 1992; CDM Regulations 2015; COSHH Regulations 2002.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for chimney breast removal?
You must assess the risks of chimney breast removal and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for chimney breast removal?
Usually Safety boots, Safety helmet, Full body harness and lanyard, FFP3 dust mask, Safety glasses, Rigger gloves, Half-mask respirator (P3 filters), Coveralls, Sun protection (sunscreen and neck cover), Hi-vis vest, Ear defenders. The site rules may add more, so check with the principal contractor.
More demolition RAMS
Related jobs in other trades
Toolbox talks for this job
Blank RAMS template: free RAMS templates. Also for other countries: Australia (SWMS) · United States (JHA) · Canada (FLHA)