Method statement for chimney breast removal

You must assess the risks of chimney breast removal and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, silica dust from concrete, brick, stone and tiles, disturbing asbestos and scaffold collapse or fall from scaffold.

RAMS example: chimney breast removal

This is a complete RAMS for chimney breast removal, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Chimney removal · Demolition · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Check flues for asbestos and soot, and isolate any gas appliance
  • Disturbing asbestos
  • Gas and fuel lines
Workers, Occupants, PublicVery high (15)
  • Before work on any building built before 2000, check the refurbishment and demolition asbestos survey for the work area (HSE HSG264). If there is none, presume asbestos is present or have it sampled before you start. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Control (engineering)
  • Most asbestos insulation, coatings and insulating board need a licensed contractor. Notifiable non-licensed work is notified to HSE before it starts. Other work needs trained workers and controls. Control (procedures)
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Control (procedures)
  • Wear a fit-tested FFP3 mask (or better) and disposable type 5 coveralls. PPE
  • Isolate and purge the line before work, with the owner's approval. Eliminate
  • Lock off and tag the isolation valve. Isolate
  • Check for leaks with a gas detector before and during work, and ventilate the area. Control (engineering)
  • Only Gas Safe registered engineers work on gas fittings. Control (procedures)
  • Remove ignition sources: no smoking, no hot work and no sparking tools near the line. Control (procedures)
  • Know where the shut-off valve is and what to do if a leak happens. Control (procedures)
  • Wear safety glasses and gloves, and keep a fire extinguisher close by. PPE
Medium (5)
2Erect scaffold around the chimney with debris protection
  • Falling from a roof edge
  • Scaffold collapse or fall from scaffold
  • Falling tools and materials
Workers, People below, PublicVery high (20)
  • Do what you can from the ground or from a scaffold at the gutter line, for example pre-assemble parts on the ground. Eliminate
  • Install edge protection or guardrails on all open roof edges before work starts. Isolate
  • Use a perimeter scaffold with handrails and toe boards along the eaves where practical. Control (engineering)
  • Where guardrails cannot be fitted, use fall restraint on certified roof anchors so workers cannot reach the edge. Control (engineering)
  • Use one safe, controlled access point and keep others off the roof. Control (procedures)
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
  • Do not overload platforms. Know the duty rating and keep material stacks over the standards. Control (procedures)
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Falling tools and materials: see step 4 for the full controls Control (procedures)
Medium (8)
3Remove bricks by hand from the top down, never undermine
  • Structural collapse during alterations
  • Demolition and falling debris
  • Lifting and carrying heavy loads
Workers, Occupants, Public, NeighboursVery high (15)
  • Get an engineer to check before removing any wall, beam, post or bracing that may be load-bearing. Eliminate
  • Keep everyone clear of the area under and next to the work. Isolate
  • Install temporary props, needles or shoring as designed before removing any support. Control (engineering)
  • Follow the engineer's sequence. Do not change it without approval. Control (procedures)
  • Check props daily. Do not remove them until the permanent support is in and approved. Control (procedures)
  • Check for asbestos, lead, live services and structural risks before demolition starts. Eliminate
  • Disconnect and cap power, gas and water before demolition. Isolate
  • Set an exclusion zone bigger than the distance the structure could fall. Isolate
  • Use a machine with a guarded cab instead of hand demolition where practical. Control (engineering)
  • Use chutes or bins to get debris down. Never drop it from height. Control (engineering)
  • Record the demolition, dismantling or strip-out arrangements in writing before work starts (CDM 2015 reg 20(2)). Control (procedures)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
Medium (6)
4Lower bricks by chute or hoist, keeping the area below closed
  • Falling tools and materials
  • Public entering the work area
Workers, Public, People below, ChildrenHigh (12)
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Use catch fans, debris netting or covered walkways where people pass below. Control (engineering)
  • Tether hand tools when working at height. Control (engineering)
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Control (procedures)
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Control (procedures)
  • Wear a hard hat anywhere objects could fall. PPE
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Control (engineering)
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Control (procedures)
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Control (procedures)
  • Use a spotter when moving plant or materials across public paths. Control (procedures)
Medium (8)
5Patch the roof the same day to keep weather out
  • Strong wind and storms
  • Falling from a roof edge
Workers, Public, People belowVery high (20)
  • Check the forecast each morning and plan work at height and lifting around the weather. Eliminate
  • Tie down or weigh down loose sheets, panels, boards and rubbish at the end of each shift. Control (engineering)
  • Set wind limits for roof work, platforms and cranes, using the manufacturer's limits, and stop when they are reached. Control (procedures)
  • Stop work and get down in lightning. Wait 30 minutes after the last thunder before going back up. Control (procedures)
  • Check scaffold, fencing and edge protection after strong wind before anyone uses them. Control (procedures)
  • Do not carry large sheets on roofs in wind. Control (procedures)
  • Wear a hard hat with a chin strap at height in windy conditions. PPE
  • Stop roof work in strong wind or rain, and when the roof is wet, icy or covered in dust or frost. Control (procedures)
  • Wear a harness clipped to a rated anchor when using restraint or fall arrest, and soft-soled non-slip boots. PPE
  • Falling from a roof edge: see step 2 for the full controls Control (procedures)
Medium (5)
6Clean up dust and debris
  • Silica dust from concrete, brick, stone and tiles
  • Poor housekeeping and waste
Workers, People nearby, VisitorsVery high (20)
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Reduce / substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Control (engineering)
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Control (procedures)
  • Do a COSHH assessment and keep exposure below the workplace exposure limit (0.1 mg/m3 respirable crystalline silica, 8 hours). Control (procedures)
  • Workers regularly exposed to silica dust get health surveillance (COSHH reg 11, HSE G404). Control (procedures)
  • Wear a fit-tested FFP3 mask. PPE
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
Medium (5)

Method statement: sequence of work

  1. Check flues for asbestos and soot, and isolate any gas appliance
  2. Erect scaffold around the chimney with debris protection
  3. Remove bricks by hand from the top down, never undermine
  4. Lower bricks by chute or hoist, keeping the area below closed
  5. Patch the roof the same day to keep weather out
  6. Clean up dust and debris

PPE

Safety bootsSafety helmetFull body harness and lanyardFFP3 dust maskSafety glassesRigger glovesHalf-mask respirator (P3 filters)CoverallsSun protection (sunscreen and neck cover)Hi-vis vestEar defenders

Plant and equipment

Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantleHand toolsBreakerGoods hoist

Permits and plans

Roof access permitWork at height permit

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for chimney breast removal

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for chimney breast removal

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Check flues for asbestos and soot, and isolate any gas appliance
  2. Erect scaffold around the chimney with debris protection
  3. Remove bricks by hand from the top down, never undermine
  4. Lower bricks by chute or hoist, keeping the area below closed
  5. Patch the roof the same day to keep weather out
  6. Clean up dust and debris

Hazards to watch on chimney breast removal

The hazards most specific to this job, and the step where each one comes up.

Step 3Demolition and falling debrisPart of a structure collapses early, or debris falls and hits workers or the public during demolition or strip out.
Step 2Scaffold collapse or fall from scaffoldA scaffold that is badly built, overloaded or altered collapses or tips, or a worker falls from an unguarded platform.
Step 1Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Step 5Strong wind and stormsWind blows sheets, panels and people off roofs and scaffolds, and storms and lightning make work at height and lifting unsafe.
Step 2, 5Falling from a roof edgeA worker slips or walks off the edge of a roof or gutter line and falls to the ground.
Step 3Structural collapse during alterationsRemoving a wall, beam, post or bracing makes part of the building fall on workers.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on chimney breast removal: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work at height, anywhere a fall could hurt them?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a scaffold or mobile tower?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: Control of Asbestos Regulations 2012; Gas Safety (Installation and Use) Regulations 1998; Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 10 (falling objects); CDM Regulations 2015, regulation 19 (stability of structures); CDM Regulations 2015, regulation 20 (demolition); Manual Handling Operations Regulations 1992; CDM Regulations 2015; COSHH Regulations 2002.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for chimney breast removal?

You must assess the risks of chimney breast removal and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for chimney breast removal?

Usually Safety boots, Safety helmet, Full body harness and lanyard, FFP3 dust mask, Safety glasses, Rigger gloves, Half-mask respirator (P3 filters), Coveralls, Sun protection (sunscreen and neck cover), Hi-vis vest, Ear defenders. The site rules may add more, so check with the principal contractor.