Method statement for hot water cylinder replacement
You must assess the risks of hot water cylinder replacement and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are electric shock from live wiring, fire from hot works, lifting and carrying heavy loads and gas and fuel lines.
RAMS example: hot water cylinder replacement
This is a complete RAMS for hot water cylinder replacement, with 10 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check access to the unit and plan the removal route through stairs, roof spaces or tight cupboards |
| Workers | High (12) |
| Medium (6) |
| 2 | Isolate power at the consumer unit and gas or water at the meter, lock off and label |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 3 | Drain the old unit, watching for scalding water and steam |
| Workers, Occupants, Visitors, Public | Medium (8) |
| Low (4) |
| 4 | Disconnect pipes, flue and wiring, and cap the gas line |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 5 | Remove the old unit using a trolley and two people |
| Workers | High (12) |
| Medium (6) |
| 6 | Position and secure the new unit on a level base |
| Workers | High (12) |
| Medium (6) |
| 7 | Make pipe joins, with a hot work permit and an extinguisher at hand if soldering or brazing |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 8 | Reconnect gas (by a Gas Safe registered engineer) and power (by a qualified electrician), then leak test |
| Workers, Occupants, Public | Very high (15) |
| Medium (5) |
| 9 | Fill and purge air, check the relief valve, commission and set the temperature |
| Workers, Occupants | Medium (8) |
| Low (4) |
| 10 | Take the old unit off site and clean up |
| Workers, Visitors | High (12) |
| Medium (6) |
Method statement: sequence of work
- Check access to the unit and plan the removal route through stairs, roof spaces or tight cupboards
- Isolate power at the consumer unit and gas or water at the meter, lock off and label
- Drain the old unit, watching for scalding water and steam
- Disconnect pipes, flue and wiring, and cap the gas line
- Remove the old unit using a trolley and two people
- Position and secure the new unit on a level base
- Make pipe joins, with a hot work permit and an extinguisher at hand if soldering or brazing
- Reconnect gas (by a Gas Safe registered engineer) and power (by a qualified electrician), then leak test
- Fill and purge air, check the relief valve, commission and set the temperature
- Take the old unit off site and clean up
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for hot water cylinder replacement
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for hot water cylinder replacement
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Isolation, lockout and test for dead done before work starts
- Hot work permit issued, extinguisher at hand, fire watch arranged
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, rigger gloves, safety glasses, FFP3 dust mask
The safe sequence of work
- Check access to the unit and plan the removal route through stairs, roof spaces or tight cupboards
- Isolate power at the consumer unit and gas or water at the meter, lock off and label
- Drain the old unit, watching for scalding water and steam
- Disconnect pipes, flue and wiring, and cap the gas line
- Remove the old unit using a trolley and two people
- Position and secure the new unit on a level base
- Make pipe joins, with a hot work permit and an extinguisher at hand if soldering or brazing
- Reconnect gas (by a Gas Safe registered engineer) and power (by a qualified electrician), then leak test
- Fill and purge air, check the relief valve, commission and set the temperature
- Take the old unit off site and clean up
Hazards to watch on hot water cylinder replacement
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for hot water cylinder replacement?
You must assess the risks of hot water cylinder replacement and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for hot water cylinder replacement?
Usually Safety boots, Rigger gloves, Safety glasses, FFP3 dust mask, Knee pads, Safety helmet, Face shield, Coveralls, Welding gauntlets, Cut-resistant gloves. The site rules may add more, so check with the principal contractor.
More plumbing RAMS
Related jobs in other trades
Toolbox talks for this job
Blank RAMS template: free RAMS templates. Also for other countries: Australia (SWMS) · United States (JHA) · Canada (FLHA)