Method statement for tanking
You must assess the risks of tanking and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, electric shock from leads and power tools, loud noise and flammable liquids and gases.
RAMS example: tanking
This is a complete RAMS for tanking, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the substrate is sheeted, clean, dry and cured, and keep occupants out of the room |
| Residents, Children, Staff, Workers, Visitors, Public | Medium (9) |
| Low (4) |
| 2 | Read the safety data sheets and set up fans or open windows, as solvent membranes give off fumes |
| Workers, Occupants | Medium (9) |
| Medium (6) |
| 3 | Have a qualified electrician isolate or make safe sockets and lights in the room if they will get wet, and run tools through RCD protection |
| Workers | High (12) |
| Low (4) |
| 4 | Prepare the surface, grinding with extraction |
| Workers, People nearby, Occupants | Very high (20) |
| Medium (6) |
| 5 | Fit bond breakers, puddle flanges and angles |
| Workers, Occupants | Medium (9) |
| Medium (6) |
| 6 | Prime the surface, keeping all ignition sources away until it is dry |
| Workers, Occupants, Public, Visitors | High (10) |
| Medium (6) |
| 7 | Apply the membrane in coats with nitrile gloves and the respirator the SDS lists (an organic vapour cartridge for solvent or polyurethane products), kneeling on pads |
| Workers, Occupants | Medium (9) |
| Medium (6) |
| 8 | Let it cure, then flood test |
| Workers, Visitors, Public | Medium (8) |
| Low (4) |
| 9 | Clean tools and dispose of waste membrane and tins properly |
| Workers, Occupants, Visitors | Medium (9) |
| Medium (6) |
Method statement: sequence of work
- Check the substrate is sheeted, clean, dry and cured, and keep occupants out of the room
- Read the safety data sheets and set up fans or open windows, as solvent membranes give off fumes
- Have a qualified electrician isolate or make safe sockets and lights in the room if they will get wet, and run tools through RCD protection
- Prepare the surface, grinding with extraction
- Fit bond breakers, puddle flanges and angles
- Prime the surface, keeping all ignition sources away until it is dry
- Apply the membrane in coats with nitrile gloves and the respirator the SDS lists (an organic vapour cartridge for solvent or polyurethane products), kneeling on pads
- Let it cure, then flood test
- Clean tools and dispose of waste membrane and tins properly
PPE
Plant and equipment
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for tanking
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for tanking
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Water suppression or on-tool extraction fitted; respirators fit tested
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: chemical-resistant gloves, safety glasses, half-mask respirator (P3 filters), knee pads
The safe sequence of work
- Check the substrate is sheeted, clean, dry and cured, and keep occupants out of the room
- Read the safety data sheets and set up fans or open windows, as solvent membranes give off fumes
- Have a qualified electrician isolate or make safe sockets and lights in the room if they will get wet, and run tools through RCD protection
- Prepare the surface, grinding with extraction
- Fit bond breakers, puddle flanges and angles
- Prime the surface, keeping all ignition sources away until it is dry
- Apply the membrane in coats with nitrile gloves and the respirator the SDS lists (an organic vapour cartridge for solvent or polyurethane products), kneeling on pads
- Let it cure, then flood test
- Clean tools and dispose of waste membrane and tins properly
Hazards to watch on tanking
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for tanking?
You must assess the risks of tanking and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for tanking?
Usually Chemical-resistant gloves, Safety glasses, Half-mask respirator (P3 filters), Knee pads, FFP3 dust mask, Safety boots, Safety goggles, Coveralls, Rigger gloves, Ear defenders, Cut-resistant gloves. The site rules may add more, so check with the principal contractor.