SWMS for site setup
Yes. Site setup usually includes high risk construction work (work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are hitting underground services, electric shock from live wiring, road traffic and being hit by mobile plant.
SWMS example: site setup
This is a complete SWMS for site setup, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Get BYDA plans and check for overhead power lines |
| Extreme |
| Medium |
| 2 | Install site fencing and signs to keep the public out |
| High |
| Medium |
| 3 | Set up toilets, first aid, fire extinguishers and the sign in area |
| High |
| Medium |
| 4 | Arrange temporary power with RCD protection |
| Extreme |
| Medium |
| 5 | Mark delivery routes and parking, away from walkways |
| Extreme |
| Medium |
| 6 | Run the site induction for every worker |
| High |
| Medium |
PPE
Plant and equipment
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for site setup
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for site setup
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Overhead lines identified and safe distances marked
- BYDA plans on site and services located
- Exclusion zone and spotter set up for plant and traffic
- Exclusion zone below the work and public kept out
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, hi-vis shirt or vest, hard hat, work gloves
The safe sequence of work
- Get BYDA plans and check for overhead power lines
- Install site fencing and signs to keep the public out
- Set up toilets, first aid, fire extinguishers and the sign in area
- Arrange temporary power with RCD protection
- Mark delivery routes and parking, away from walkways
- Run the site induction for every worker
Hazards to watch on site setup
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Work in an area with movement of powered mobile plant
Equipment on this job that needs a licence, ticket or training:
- Skid steer (Bobcat): Verification of competency (VOC) for the machine
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulation 2011, regulation 43 (emergency plans); WHS Regulation 2011, Part 4.7 and AS/NZS 3012; WHS Regulation 2011, Part 4.7 General electrical safety; WHS Regulation 2011, Part 5.1 Plant; WHS Regulation 2011, regulation 48 (remote or isolated work).
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for site setup?
Yes. Site setup usually includes high risk construction work (work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for site setup?
Usually Steel cap boots, Hi-vis shirt or vest, Hard hat, Work gloves. The site rules may add more, so check with the principal contractor.