Yes. Trenching usually includes high risk construction work (work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are hitting underground services, being hit by mobile plant, road traffic and trench or excavation collapse.

SWMS example: trenching

This is a complete SWMS for trenching, with 10 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Trenching for services · Excavation and earthworks · Example
Document SWMS-001 · Rev 1

High risk construction work covered

Work in an area with movement of powered mobile plant

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Get BYDA plans, then locate and mark services on the ground
  • Hitting underground services
  • Gas and fuel lines
Extreme
  • Keep machine buckets well clear of marked services and use a spotter. Isolate
  • Scan the area with a cable locator before digging and mark services on the ground. Engineering
  • Hand dig or vacuum excavate to expose services before using a machine near them. Engineering
  • Lodge a free BYDA (Before You Dig Australia) request and get the plans before any digging. Administrative
  • Keep plans or locate tickets on site and check them again if the work area grows. Administrative
  • If you hit a service, stop, get everyone clear, and call the owner and emergency services. Administrative
  • Wear safety boots, gloves and hi-vis when digging. PPE
  • Isolate and purge the line before work, with the owner's approval. Eliminate
  • Lock off and tag the isolation valve. Isolate
  • Check for leaks with a gas detector before and during work, and ventilate the area. Engineering
  • Only licensed gasfitters work on gas lines. Administrative
  • Remove ignition sources: no smoking, no hot work and no sparking tools near the line. Administrative
  • Know where the shut-off valve is and what to do if a leak happens. Administrative
  • Wear safety glasses and gloves, and keep a fire extinguisher close by. PPE
Medium
2Check for overhead power lines and plan where the machine and spoil will go
  • Contact with overhead power lines
  • Being hit by mobile plant
Extreme
  • Ask the network operator to turn off, move or insulate the lines before work starts. Eliminate
  • Use non-conductive (fibreglass) ladders near any power lines. Substitute
  • Mark the safe distance with flags, tape or goal posts and keep all plant and people outside it. Isolate
  • Keep out of the No Go Zone set by your state and the network operator, or get written approval and a safety observer. In NSW and Qld, untrained people and plant stay at least 3 m from lines on poles up to 132 kV, 6 m up to 330 kV and 8 m above 330 kV. In Victoria the limits differ, and work within 8 m of tower lines needs a spotter and the network operator's permission. Administrative
  • Use a dedicated spotter whenever plant moves or raises anything near lines. Administrative
  • Treat all lines as live. If plant touches a line, stay in the cab and keep everyone well away. Administrative
  • Separate people and plant with barriers, exclusion zones and marked walkways. Isolate
  • Use plant with working reversing alarms, cameras and lights. Engineering
  • Have a traffic management plan showing plant routes, loading areas and pedestrian paths. Administrative
  • Use a spotter when reversing or working near people. Administrative
  • Make eye contact with the operator before going near. Stay out of the swing radius. Administrative
  • Operators hold a High Risk Work Licence where needed (for example forklift) and are trained and assessed on other plant. Administrative
  • Do a pre-start check on each machine every day and record it. Administrative
  • Wear hi-vis clothing and a hard hat. PPE
Medium
3Pothole by hand or vacuum to expose marked services
  • Hitting underground services
  • Lifting and carrying heavy loads
Extreme
  • Hitting underground services: see step 1 for the full controls Administrative
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium
4Set an exclusion zone and a spotter around the excavator
  • Being hit by mobile plant
  • Road traffic
Extreme
  • Being hit by mobile plant: see step 2 for the full controls Administrative
  • Do the work at low-traffic times, or close the road or lane with approval. Eliminate
  • Put solid barriers between the work and traffic where speeds are high, not just cones. Isolate
  • Use a truck-mounted attenuator or buffer vehicle on high speed roads. Engineering
  • Have a Traffic Management Plan. Signs and cones are set out by accredited traffic controllers to your state's rules. Administrative
  • Get a road occupancy or street works permit from the road authority before you start. Administrative
  • Park work vehicles to shield the work zone, with beacons on. Administrative
  • Wear day and night hi-vis clothing (AS/NZS 4602.1). PPE
Medium
5Dig the trench, keeping spoil back from the edge
  • Trench or excavation collapse
  • Being hit by mobile plant
Extreme
  • Use methods that keep people out of the trench, such as directional boring or working from the surface. Eliminate
  • Barricade or cover the excavation so people and plant cannot fall in. Isolate
  • Trench or excavation collapse: see step 6 for the full controls Administrative
  • Being hit by mobile plant: see step 2 for the full controls Administrative
Medium
6Shore, bench or batter any trench 1.5 m deep or more before anyone goes in, unless a geotechnical engineer advises in writing that it is safe
  • Trench or excavation collapse
Extreme
  • Use methods that keep people out of the trench, such as directional boring or working from the surface. Eliminate
  • Barricade or cover the excavation so people and plant cannot fall in. Isolate
  • Shore, bench or batter the walls of any trench 1.5 metres deep or more before anyone goes in, unless a geotechnical engineer advises in writing that the sides are safe. Engineering
  • Keep spoil, materials and plant at least 1 metre back from the edge. Engineering
  • Provide a safe way in and out, such as a ladder near where people work. Engineering
  • Inspect the excavation at the start of each shift and after rain or anything that could weaken it. Record it. Administrative
  • Never work alone in a trench. Watch for water, cracks and bulging walls, and get out if you see them. Administrative
  • Wear a hard hat, hi-vis and safety boots. PPE
Medium
7Barricade the trench and provide safe ladder access, pump out any water, and keep engine and pump exhaust away from the trench
  • Public entering the work area
  • Falling from a ladder
High
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Engineering
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Administrative
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Administrative
  • Use a spotter when moving plant or materials across public paths. Administrative
  • Use a platform ladder, mobile scaffold or EWP for longer jobs instead of a straight ladder. Substitute
  • Use industrial-rated ladders (AS/NZS 1892, 120 kg or more) in good condition. Remove any damaged ladder from site. Engineering
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Engineering
  • Use ladders only for short, light work. Do not carry heavy or awkward loads up a ladder. Administrative
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Administrative
  • Do not stand on the top three rungs of an extension ladder or the top step of a stepladder. Administrative
  • Check the ladder before each use: feet, rungs, stiles and locks. Administrative
  • Wear non-slip safety boots with clean soles. PPE
Medium
8Inspect the trench at the start of each shift and after rain
  • Trench or excavation collapse
Extreme
  • Trench or excavation collapse: see step 6 for the full controls Administrative
Medium
9Lay services, then backfill and compact in layers
  • Trench or excavation collapse
  • Hand-arm and whole-body vibration
  • Loud noise
  • Lifting and carrying heavy loads
Extreme
  • Trench or excavation collapse: see step 6 for the full controls Administrative
  • Use low-vibration tools and methods, such as a breaker on an excavator instead of a hand jackhammer. Substitute
  • Keep tools sharp and well maintained, and use anti-vibration handles and seats. Engineering
  • Limit trigger time on high-vibration tools and rotate workers. Administrative
  • Keep hands warm and dry, and take regular breaks. Administrative
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • Keep exposure below 85 dB(A) over 8 hours. Give hearing tests to workers who often need hearing protection. Administrative
  • Lifting and carrying heavy loads: see step 3 for the full controls Administrative
Medium
10Reinstate the surface and clean up the road and footpath
  • Poor housekeeping and waste
  • Road traffic
Extreme
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
  • Road traffic: see step 4 for the full controls Administrative
Medium

PPE

Steel cap bootsHi-vis shirt or vestHard hatSafety glassesHearing protection (earmuffs or plugs)Work gloves

Plant and equipment

Excavator: Verification of competency (VOC) for the machineWacker plateHand toolsTipper or site dumper: Driver licence for the vehicle class, VOC for site dumpers

Permits and plans

Excavation / dig permit

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Page 1 of the free trenching SWMS template: business details, high risk construction work and job steps with hazards, risk ratings and controls

Free SWMS template for trenching

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for trenching

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Get BYDA plans, then locate and mark services on the ground
  2. Check for overhead power lines and plan where the machine and spoil will go
  3. Pothole by hand or vacuum to expose marked services
  4. Set an exclusion zone and a spotter around the excavator
  5. Dig the trench, keeping spoil back from the edge
  6. Shore, bench or batter any trench 1.5 m deep or more before anyone goes in, unless a geotechnical engineer advises in writing that it is safe
  7. Barricade the trench and provide safe ladder access, pump out any water, and keep engine and pump exhaust away from the trench
  8. Inspect the trench at the start of each shift and after rain
  9. Lay services, then backfill and compact in layers
  10. Reinstate the surface and clean up the road and footpath

Hazards to watch on trenching

The hazards most specific to this job, and the step where each one comes up.

Step 4, 10Road trafficPassing cars and trucks hit workers or plant working on or next to a road.
Step 5, 6, 8, 9Trench or excavation collapseThe trench walls cave in and bury or crush a worker. Trenches 1.5 metres deep or more must be shored, benched or battered unless a geotechnical engineer advises in writing that the sides are safe.
Step 2Contact with overhead power linesA ladder, EWP, crane, tipper or long length of material touches or gets close to an overhead line and electrocutes people.
Step 1Gas and fuel linesDamaging or opening a gas or fuel line causes a leak, fire or explosion.
Step 9Hand-arm and whole-body vibrationLong periods on jackhammers, grinders, compactors or riding plant cause white finger, numbness and back damage.
Step 1, 3Hitting underground servicesDigging, drilling or driving pegs hits a buried power cable, gas pipe or water main, causing electrocution, explosion or flooding.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on trenching: Extreme before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (possible and catastrophic becomes unlikely and major).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work more than 2 metres off the ground?
  • Will anyone work on a roof?
  • Is there a skylight, clear sheet, fibro or other fragile roofing?
  • Will you use a scaffold or mobile tower?
  • Will you use an EWP (scissor lift or boom lift)?

Licences and legal requirements in Australia

This task can involve these high risk construction work categories under the WHS Regulations:

  • Work in an area with movement of powered mobile plant

Equipment on this job that needs a licence, ticket or training:

  • Excavator: Verification of competency (VOC) for the machine
  • Tipper or site dumper: Driver licence for the vehicle class, VOC for site dumpers

A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.

Rules that apply: WHS Regulation 2011, Part 5.1 Plant; WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulations, Part 6.3 Division 3 (Excavation work, r.304 to 306); WHS Regulation 2011, Part 4.4 Falls; WHS Regulation 2011, Part 4.1 Noise.

Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for trenching?

Yes. Trenching usually includes high risk construction work (work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for trenching?

Usually Steel cap boots, Hi-vis shirt or vest, Hard hat, Safety glasses, Hearing protection (earmuffs or plugs), Work gloves. The site rules may add more, so check with the principal contractor.