What are RAMS (Risk Assessment and Method Statement)?

RAMS stands for Risk Assessment and Method Statement: a risk assessment that records the hazards of a job, who could be harmed and the controls, paired with a method statement that sets out step by step how the work will be done safely.

What goes in each part

The risk assessment follows HSE's five steps: identify the hazards, assess the risks (who might be harmed and how, what you already do, what more is needed), control the risks, record the findings, and review the controls.

The method statement, in HSE's words, draws together the hazards and controls from the risk assessment and describes in a logical sequence exactly how a job is to be carried out. It can include the company's health and safety organisation, training, and arrangements for serious or imminent danger. HSE notes that the most effective method statements often include diagrams.

Who writes and signs RAMS

The contractor doing the work writes the RAMS, because the MHSWR duty is on the employer or self-employed person doing the work. It should be written by someone who knows the job, with input from the people who will do it; HSE says to involve your employees, as they usually have good ideas. You can do it yourself or appoint a competent person to help.

The law does not prescribe signatures. In practice the author and a manager sign it, the principal contractor signs to accept it, and every worker signs a briefing record. That record is your evidence that you gave workers the information reg 15(9) requires.

When RAMS must be reviewed

MHSWR reg 3(3) says the assessment must be reviewed if there is reason to suspect it is no longer valid or there has been a significant change, and changed where the review shows it needs to be. HSE adds: review the controls to make sure they work, and review when staff, processes, substances or equipment change, when workers spot problems, or after accidents or near misses.

HSE says that where a similar operation is repeated the method statement will be similar from job to job, but where circumstances change markedly it should be revised for each job.

How long to keep RAMS

Neither MHSWR reg 3 nor CDM 2015 reg 15 sets a retention period for RAMS. Keep the current version and the signed briefing record on site for the whole job, keep every revision, and keep a copy in your records afterwards in case of a claim, an investigation or a principal contractor audit.

Common mistakes

These are the faults principal contractors send back most.

  • A method statement that is just a list of headings, with nothing on how each step is done.
  • A method sequence that does not match the risk assessment.
  • Copying an example and adding your company name. HSE says this would not satisfy the law.
  • No reference to the asbestos survey on refurbishment of older buildings.
  • Residual risks left at High with no explanation.
  • No briefing record, so there is no evidence the crew was told.
  • Not revising it when the job changes.