Method statement for retaining wall construction
You must assess the risks of retaining wall construction and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, hitting underground services, trench or excavation collapse and being hit by mobile plant.
RAMS example: retaining wall construction
This is a complete RAMS for retaining wall construction, with 10 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Get utility plans and check the wall has an engineer's design where needed, such as most walls over 1 m or any wall holding up a building, driveway or slope |
| Workers, Public | Very high (15) |
| Medium (5) |
| 2 | Check neighbouring footings, fences and structures near the cut, and get engineer advice before digging close enough to undermine them |
| Workers, Public, Children | Very high (15) |
| Medium (5) |
| 3 | Set up an exclusion zone around the machines |
| Workers, Visitors, Public | Very high (15) |
| Medium (5) |
| 4 | Excavate the cut in short sections, battered or benched to the engineer's or geotechnical advice, and never let anyone work between an unsupported cut face and the wall |
| Workers, Visitors, Public | Very high (15) |
| Medium (5) |
| 5 | Pour the footing or lay the base, capping any rebar bars |
| Workers | High (12) |
| Low (4) |
| 6 | Lay drainage and the first course |
| Workers | High (12) |
| Medium (6) |
| 7 | Lift blocks or sleepers with machines or two people |
| Workers, Visitors, Public | Very high (15) |
| Medium (6) |
| 8 | Cut blocks wet, never dry |
| Workers, People nearby | Very high (20) |
| Medium (8) |
| 9 | Backfill and compact behind the wall in layers as it goes up |
| Workers, Visitors, Public | Very high (15) |
| Medium (6) |
| 10 | Barricade the top of the wall until the permanent fence or balustrade is in, then clean up |
| Public, Children, Workers, Visitors | High (12) |
| Low (4) |
Method statement: sequence of work
- Get utility plans and check the wall has an engineer's design where needed, such as most walls over 1 m or any wall holding up a building, driveway or slope
- Check neighbouring footings, fences and structures near the cut, and get engineer advice before digging close enough to undermine them
- Set up an exclusion zone around the machines
- Excavate the cut in short sections, battered or benched to the engineer's or geotechnical advice, and never let anyone work between an unsupported cut face and the wall
- Pour the footing or lay the base, capping any rebar bars
- Lay drainage and the first course
- Lift blocks or sleepers with machines or two people
- Cut blocks wet, never dry
- Backfill and compact behind the wall in layers as it goes up
- Barricade the top of the wall until the permanent fence or balustrade is in, then clean up
PPE
Plant and equipment
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for retaining wall construction
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for retaining wall construction
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Utility plans checked and area scanned with CAT and Genny
- Trench support, benching or battering in place; spoil kept back from the edge
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone and spotter set up for plant and traffic
- Exclusion zone below the work and public kept out
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, hi-vis vest, rigger gloves, safety glasses
The safe sequence of work
- Get utility plans and check the wall has an engineer's design where needed, such as most walls over 1 m or any wall holding up a building, driveway or slope
- Check neighbouring footings, fences and structures near the cut, and get engineer advice before digging close enough to undermine them
- Set up an exclusion zone around the machines
- Excavate the cut in short sections, battered or benched to the engineer's or geotechnical advice, and never let anyone work between an unsupported cut face and the wall
- Pour the footing or lay the base, capping any rebar bars
- Lay drainage and the first course
- Lift blocks or sleepers with machines or two people
- Cut blocks wet, never dry
- Backfill and compact behind the wall in layers as it goes up
- Barricade the top of the wall until the permanent fence or balustrade is in, then clean up
Hazards to watch on retaining wall construction
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Excavator (360): CPCS or NPORS excavator card
- Skid steer loader: CPCS or NPORS skid steer card
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: HSE HSG47 Avoiding danger from underground services; CDM Regulations 2015, regulation 22 (excavations); CDM Regulations 2015; CDM Regulations 2015 and PUWER 1998; Manual Handling Operations Regulations 1992; COSHH Regulations 2002; Provision and Use of Work Equipment Regulations 1998 (PUWER); Control of Noise at Work Regulations 2005; Control of Vibration at Work Regulations 2005.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for retaining wall construction?
You must assess the risks of retaining wall construction and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for retaining wall construction?
Usually Safety boots, Hi-vis vest, Rigger gloves, Safety glasses, Ear defenders, FFP3 dust mask, Safety helmet, Chemical-resistant gloves, Safety goggles, Knee pads, Half-mask respirator (P3 filters). The site rules may add more, so check with the principal contractor.