Method statement for suspended ceiling installation
You must assess the risks of suspended ceiling installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are silica dust from concrete, brick, stone and tiles, MEWP tip-over or crush, falling tools and materials and loud noise.
RAMS example: suspended ceiling installation
This is a complete RAMS for suspended ceiling installation, with 4 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Plan MEWP use and close the area below |
| Workers, People nearby, Public, People below | Very high (15) |
| Medium (8) |
| 2 | Drill fixings into the slab with dust extraction |
| Workers, People nearby | Very high (20) |
| Medium (6) |
| 3 | Hang grid and wires, watching sharp grid ends |
| Workers | Medium (9) |
| Medium (6) |
| 4 | Drop in tiles and clean up |
| Workers, Occupants, Visitors | Medium (8) |
| Low (4) |
Method statement: sequence of work
- Plan MEWP use and close the area below
- Drill fixings into the slab with dust extraction
- Hang grid and wires, watching sharp grid ends
- Drop in tiles and clean up
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for suspended ceiling installation
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for suspended ceiling installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- MEWP pre-use check done and the operator holds an IPAF card
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone below the work and public kept out
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety glasses, safety helmet, FFP3 dust mask
The safe sequence of work
- Plan MEWP use and close the area below
- Drill fixings into the slab with dust extraction
- Hang grid and wires, watching sharp grid ends
- Drop in tiles and clean up
Hazards to watch on suspended ceiling installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Scissor lift (MEWP): IPAF PAL card (3a)
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Work at Height Regulations 2005 and LOLER 1998; Work at Height Regulations 2005, regulation 10 (falling objects); COSHH Regulations 2002; Control of Noise at Work Regulations 2005; Provision and Use of Work Equipment Regulations 1998 (PUWER).
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for suspended ceiling installation?
You must assess the risks of suspended ceiling installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for suspended ceiling installation?
Usually Safety boots, Safety glasses, Safety helmet, FFP3 dust mask, Cut-resistant gloves, Full body harness and lanyard, Hi-vis vest, Half-mask respirator (P3 filters), Ear defenders, Rigger gloves, Knee pads. The site rules may add more, so check with the principal contractor.