Method statement for external rendering

You must assess the risks of external rendering and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, scaffold collapse or fall from scaffold, heat stress and sun exposure (UV).

RAMS example: external rendering

This is a complete RAMS for external rendering, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
External rendering · Plastering and dry lining · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Use scaffold with guardrails, not ladders
  • Falling from height
  • Scaffold collapse or fall from scaffold
Workers, People below, PublicVery high (20)
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile tower or MEWP instead of working off a ladder. Control (engineering)
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Control (engineering)
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Control (procedures)
  • Wear a full body harness with a shock-absorbing lanyard, clipped on at all times when using fall arrest. PPE
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
  • Do not overload platforms. Know the duty rating and keep material stacks over the standards. Control (procedures)
  • Never remove ties, braces, guardrails or boards. Only the scaffolder alters the scaffold. Control (procedures)
  • Wear a hard hat and safety boots on and around the scaffold. PPE
Medium (5)
2Mix render with gloves and goggles
  • Wet concrete and cement burns
  • General dust
  • Eye injuries
Workers, Occupants, People nearbyMedium (9)
  • Use long-handled tools and pumps to cut down contact. Control (engineering)
  • Wash concrete off skin straight away with clean water. Control (procedures)
  • Have clean water and eye wash where concrete or mortar is mixed and used. Control (procedures)
  • Do a COSHH assessment for cement, lime and mortar, and check hands regularly for early signs of dermatitis. Control (procedures)
  • Wear waterproof gloves, long sleeves and waterproof boots with trousers worn over the top. PPE
  • Wear safety glasses or goggles to stop splashes. PPE
  • Use low-dust products, such as dust-reduced or pre-mixed compounds. Reduce / substitute
  • Seal off the work area with plastic sheeting in occupied buildings. Isolate
  • Use tools with dust extraction and a vacuum for clean up. Control (engineering)
  • Lightly mist the area with water to keep dust down, away from anything electrical. Control (engineering)
  • Never dry sweep or blow dust off with compressed air. Control (procedures)
  • Use tool guards and screens to stop flying particles. Control (engineering)
  • Use dust extraction and water to keep dust out of the air. Control (engineering)
  • Keep others out of the area when cutting, grinding or chipping. Control (procedures)
  • Keep an eye wash station or eye wash bottles on site. Control (procedures)
  • Wear safety glasses at all times, goggles for dust and chemicals, and a face shield for grinding. PPE
Low (4)
3Apply render, avoiding skin contact
  • Wet concrete and cement burns
  • Repetitive work and awkward postures
WorkersMedium (9)
  • Wet concrete and cement burns: see step 2 for the full controls Control (procedures)
  • Use tools that cut the effort: powered screwdrivers, long-handled tools and extension poles for overhead work. Reduce / substitute
  • Set work up at waist height on benches or trestles where you can. Control (engineering)
  • Use light tools with good grips, and keep blades and bits sharp. Control (engineering)
  • Rotate tasks and take short breaks every hour on repetitive work. Control (procedures)
  • Warm up before heavy physical work and report aches and pains early. Control (procedures)
  • Wear knee pads for kneeling work and gloves for grip. PPE
Medium (6)
4Watch for heat and sun
  • Heat stress
  • Sun exposure (UV)
WorkersHigh (12)
  • Schedule heavy work for the cooler part of the day. Eliminate
  • Provide shade over work and rest areas, and fans or cooling in roof spaces. Control (engineering)
  • Supply cool drinking water close by and drink a cup every 15 to 20 minutes. Control (procedures)
  • Take regular rest breaks in the shade, more often as it gets hotter. Control (procedures)
  • Let new and returning workers build up to full work in the heat over about a week. Control (procedures)
  • Watch each other for dizziness, headache, confusion or stopping sweating. Stop work, cool down and get help. Control (procedures)
  • Have a hot weather plan, including when work stops. Control (procedures)
  • Wear light, loose, long-sleeved clothing, a hat or brim, and sunscreen. PPE
  • Plan outdoor work for early morning or late afternoon when UV is lower. Eliminate
  • Put shade covers over fixed work areas. Control (engineering)
  • Check the UV index each day. Use sun protection when it is 3 or higher. Control (procedures)
  • Check your skin regularly and see a doctor about any new or changing spots. Control (procedures)
  • Wear a broad-brim hat or hard hat brim, long sleeves, sunglasses and SPF 30 or higher sunscreen, reapplied every 2 hours. PPE
Medium (8)
5Clean the scaffold and area
  • Poor housekeeping and waste
  • Falling tools and materials
Workers, Visitors, Public, People belowHigh (12)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Use catch fans, debris netting or covered walkways where people pass below. Control (engineering)
  • Tether hand tools when working at height. Control (engineering)
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Control (procedures)
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Control (procedures)
  • Wear a hard hat anywhere objects could fall. PPE
Medium (8)

Method statement: sequence of work

  1. Use scaffold with guardrails, not ladders
  2. Mix render with gloves and goggles
  3. Apply render, avoiding skin contact
  4. Watch for heat and sun
  5. Clean the scaffold and area

PPE

Safety bootsChemical-resistant glovesSafety gogglesFFP3 dust maskSun protection (sunscreen and neck cover)Safety helmetHi-vis vestKnee padsSafety glassesFace shieldRigger gloves

Plant and equipment

Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantleCement mixerAirless paint sprayerHand tools

Permits and plans

Work at height permit

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for external rendering

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for external rendering

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Use scaffold with guardrails, not ladders
  2. Mix render with gloves and goggles
  3. Apply render, avoiding skin contact
  4. Watch for heat and sun
  5. Clean the scaffold and area

Hazards to watch on external rendering

The hazards most specific to this job, and the step where each one comes up.

Step 1Scaffold collapse or fall from scaffoldA scaffold that is badly built, overloaded or altered collapses or tips, or a worker falls from an unguarded platform.
Step 4Sun exposure (UV)Long hours in the sun cause sunburn, eye damage and skin cancer.
Step 2, 3Wet concrete and cement burnsWet concrete, mortar and cement burn skin and eyes. Burns can be deep and are often not felt until later.
Step 4Heat stressHard work in hot weather or hot roof spaces causes heat exhaustion or heat stroke, which can kill.
Step 2Eye injuriesFlying chips, dust, chemicals or sparks get into the eye and cause damage or blindness.
Step 2General dustDust from plasterboard, filler, cement and clean up irritates eyes and lungs and makes it hard to see.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on external rendering: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a MEWP (scissor lift or cherry picker)?
  • Was the building built before 2000?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 10 (falling objects).

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for external rendering?

You must assess the risks of external rendering and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for external rendering?

Usually Safety boots, Chemical-resistant gloves, Safety goggles, FFP3 dust mask, Sun protection (sunscreen and neck cover), Safety helmet, Hi-vis vest, Knee pads, Safety glasses, Face shield, Rigger gloves. The site rules may add more, so check with the principal contractor.