JHA for site grading
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for site grading before you start.
A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are silica dust from concrete, brick, stone and tiles, hitting underground services, road traffic and being hit by heavy equipment.
JHA example: site grading
This is a complete JHA for site grading, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Get 811 locates, check for overhead power lines and plan truck movements |
| Critical |
| Medium |
| 2 | Set up a spotter and exclusion zones for machines |
| Critical |
| Medium |
| 3 | Cut the site, battering or retaining cut faces |
| Critical |
| Medium |
| 4 | Watch neighbouring fences and footings near the cut |
| High |
| Medium |
| 5 | Control dust with water |
| Critical |
| Medium |
| 6 | Load trucks and clean the street |
| Critical |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this JHA.
Free JHA template for site grading
Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for site grading
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- JHA read, explained and signed by everyone on the job
- Overhead lines identified and safe distances marked
- 811 ticket current and services marked
- Shoring, sloping, benching or a trench box in place; spoil kept back from the edge
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone and spotter set up for equipment and traffic
- Exclusion zone below the work and public kept out
- First aid / CPR person, first aid kit and emergency number (911) confirmed
- PPE checked and worn: safety-toe boots (ASTM F2413), high-visibility safety apparel, ANSI/ISEA 107 class 2 or 3 (type r near roadways), hard hat (ANSI Z89.1), hearing protection (earmuffs or plugs)
The safe sequence of work
- Get 811 locates, check for overhead power lines and plan truck movements
- Set up a spotter and exclusion zones for machines
- Cut the site, battering or retaining cut faces
- Watch neighbouring fences and footings near the cut
- Control dust with water
- Load trucks and clean the street
Hazards to watch on site grading
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work 6 feet or more above a lower level?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, fiberglass panel or other fragile roofing?
- Will you use a scaffold or rolling tower?
Licences and legal requirements in United States
Equipment on this job that needs a licence, ticket or training:
- Dump truck: CDL if the truck's GVWR, or the combination's GCWR, is 26,001 lb or more (49 CFR 383.5), or if it carries placarded hazmat
OSHA requires employers to find and fix hazards and to train workers on them. A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew. General contractors often require one before you start.
Rules that apply: 29 CFR 1926.651(b) and your state 811 law; 29 CFR 1926.1408 and 1926.416; MUTCD Part 6 and 29 CFR 1926 Subpart G; 29 CFR 1926 Subpart O; 29 CFR 1926 Subpart P; 29 CFR 1926.1153.
Why JHAs get rejected
General contractors send documents back for these reasons. This example avoids them, but check yours too.
- Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
- No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
- No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
- Equipment listed without inspection requirements, and no training listed for the people using it.
- Respirators listed with no respiratory protection program, medical clearance or fit test.
- Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
- No crew sign-off, or no date and revision when the job has changed.
Questions
Do I need a JHA for site grading?
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for site grading before you start.
Who signs the JHA?
The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.
How long do I keep it?
Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.
What PPE is needed for site grading?
Usually Safety-toe boots (ASTM F2413), High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways), Hard hat (ANSI Z89.1), Hearing protection (earmuffs or plugs), N95 respirator, Safety glasses (ANSI Z87.1), Half-face respirator (P100 cartridges), Work gloves. The site rules may add more, so check with the general contractor.