SWMS for brick wall repair

A SWMS is required by law if brick wall repair includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from height, silica dust from concrete, brick, stone and tiles, public entering the work area and angle grinder injuries.

SWMS example: brick wall repair

This is a complete SWMS for brick wall repair, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Brick wall repair and crack stitching · Bricklaying · Example
Document SWMS-001 · Rev 1

High risk construction work covered

None for this task on its own. Tick any that apply on your site.

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Check the wall is stable and prop it if it is leaning
  • Structural collapse during alterations
High
  • Get an engineer to check before removing any wall, beam, post or bracing that may be load-bearing. Eliminate
  • Keep everyone clear of the area under and next to the work. Isolate
  • Install temporary props, needles or shoring as designed before removing any support. Engineering
  • Follow the engineer's sequence. Do not change it without approval. Administrative
  • Check props daily. Do not remove them until the permanent support is in and approved. Administrative
  • Install temporary support to the engineer's or temporary works design before any load bearing element is altered. Administrative
  • Wear a hard hat and safety boots. PPE
Medium
2Set up access and barricades
  • Falling from height
  • Public entering the work area
Extreme
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile work platform or EWP instead of working off a ladder. Engineering
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Engineering
  • Everyone working at height holds a White Card and has been briefed on this SWMS before going up. Administrative
  • Have a written emergency and rescue plan, tested before work starts, so a worker hanging in a harness can be brought down within minutes (WHS Regulations r.80). Administrative
  • Wear a full body harness with a shock-absorbing lanyard, clipped on at all times when using fall arrest. PPE
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Engineering
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Administrative
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Administrative
  • Use a spotter when moving plant or materials across public paths. Administrative
Medium
3Cut out damaged bricks and slots with dust extraction
  • Silica dust from concrete, brick, stone and tiles
  • Angle grinder injuries
  • Loud noise
Extreme
  • If the job involves engineered stone: do not supply, fabricate or install engineered stone benchtops, panels or slabs (banned since 1 July 2024). Removing, repairing or making minor changes to existing engineered stone is only allowed with water suppression or on-tool extraction, a fitted respirator, and written notice to the regulator before the work starts. Eliminate
  • Order materials cut to size, or use low-dust methods such as score and snap or a block splitter. Substitute
  • Cut outdoors or in a separate area, with other people well away and upwind. Isolate
  • Use water on the blade or on-tool dust extraction connected to an H-class vacuum. Engineering
  • Clean up with a vacuum or wet methods. Never dry sweep or use compressed air. Administrative
  • If the cutting, grinding or drilling is high risk, prepare a silica risk control plan (or include the r.529CA assessment in this SWMS), train workers in silica risks and give them the plan before work starts. Administrative
  • Wear a fit-tested P2 (or better) respirator. PPE
  • Use a guarded saw or a different tool where you can. Substitute
  • Keep the guard on and use the side handle. Never remove the guard. Engineering
  • Use the right disc for the job, rated for the grinder's speed. Check it for cracks first. Administrative
  • Only trained people change discs, with the grinder unplugged or the battery out. Administrative
  • Keep both hands on the grinder and let the disc stop before putting it down. Administrative
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • If you have to shout to be heard 1 metre away, wear hearing protection. Administrative
  • Keep exposure below 85 dB(A) over 8 hours. Give hearing tests to workers who often need hearing protection. Administrative
Medium
4Fit new bricks or helical bars with resin
  • Hazardous chemicals
  • Lifting and carrying heavy loads
High
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Read the Safety Data Sheet (SDS) before use and keep a register of hazardous chemicals on site. Administrative
  • Keep chemicals in labelled containers. Never decant into drink bottles. Administrative
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Administrative
  • Have eye wash and a spill kit nearby, and wash hands before eating. Administrative
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Rotate tasks and take breaks on long lifting jobs. Administrative
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium
5Repoint and clean up
  • Poor housekeeping and waste
Medium
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Low

PPE

Steel cap bootsSafety glassesP2 dust maskHearing protection (earmuffs or plugs)Work glovesHi-vis shirt or vestHalf-face respirator (P2 or P3 filters)Face shieldCut-resistant glovesChemical-resistant gloves (nitrile)Safety gogglesOveralls

Plant and equipment

Angle grinderRotary hammer drillMobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 mHand tools

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Free SWMS template for brick wall repair

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for brick wall repair

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Check the wall is stable and prop it if it is leaning
  2. Set up access and barricades
  3. Cut out damaged bricks and slots with dust extraction
  4. Fit new bricks or helical bars with resin
  5. Repoint and clean up

Hazards to watch on brick wall repair

The hazards most specific to this job, and the step where each one comes up.

Step 3Angle grinder injuriesThe disc shatters, binds or kicks back, causing deep cuts to legs and hands or eye injuries.
Step 1Structural collapse during alterationsRemoving a wall, beam, post or bracing makes part of the building fall on workers.
Step 4Hazardous chemicalsGlues, sealants, solvents, acids, cleaners and cement burn skin and eyes or cause breathing problems and poisoning.
Step 2Falling from heightA worker falls more than 2 metres from an edge, platform or opening and is badly hurt or killed.
Step 3Silica dust from concrete, brick, stone and tilesCutting, grinding or drilling concrete, brick, stone, tiles or fibre cement makes fine silica dust that causes silicosis and lung cancer.
Step 2Public entering the work areaMembers of the public, including children, walk into the site and are hit by plant or falling objects, or fall into holes.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on brick wall repair: Extreme before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (likely and catastrophic becomes unlikely and major).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work more than 2 metres off the ground?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a skylight, clear sheet, fibro or other fragile roofing?
  • Will you use a scaffold or mobile tower?

Licences and legal requirements in Australia

Equipment on this job that needs a licence, ticket or training:

  • Mobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 m

A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.

Rules that apply: WHS Regulation 2011, Part 4.4 Falls; WHS Regulations, Chapter 8A (Crystalline silica substances and engineered stone); WHS Regulation 2011, Part 4.1 Noise; WHS Regulation 2011, Chapter 7 Hazardous chemicals; WHS Regulation 2011, Part 4.2 Hazardous manual tasks.

Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for brick wall repair?

A SWMS is required by law if brick wall repair includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for brick wall repair?

Usually Steel cap boots, Safety glasses, P2 dust mask, Hearing protection (earmuffs or plugs), Work gloves, Hi-vis shirt or vest, Half-face respirator (P2 or P3 filters), Face shield, Cut-resistant gloves, Chemical-resistant gloves (nitrile), Safety goggles, Overalls. The site rules may add more, so check with the principal contractor.