SWMS for fascia and soffit replacement

A SWMS is required by law if fascia and soffit replacement includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from height, disturbing asbestos, public entering the work area and falling from a ladder.

SWMS example: fascia and soffit replacement

This is a complete SWMS for fascia and soffit replacement, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Replace fascia and soffits · Roofing · Example
Document SWMS-001 · Rev 1

High risk construction work covered

None for this task on its own. Tick any that apply on your site.

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Barricade below and set up a mobile scaffold or secured ladder
  • Public entering the work area
  • Falling from a ladder
  • Falling from height
Extreme
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Engineering
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Administrative
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Administrative
  • Use a platform ladder, mobile scaffold or EWP for longer jobs instead of a straight ladder. Substitute
  • Use industrial-rated ladders (AS/NZS 1892, 120 kg or more) in good condition. Remove any damaged ladder from site. Engineering
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Engineering
  • Use ladders only for short, light work. Do not carry heavy or awkward loads up a ladder. Administrative
  • Keep three points of contact and your belt buckle between the stiles. Do not overreach. Administrative
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile work platform or EWP instead of working off a ladder. Engineering
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Engineering
  • Everyone working at height holds a White Card and has been briefed on this SWMS before going up. Administrative
  • Have a written emergency and rescue plan, tested before work starts, so a worker hanging in a harness can be brought down within minutes (WHS Regulations r.80). Administrative
Medium
2Check soffit sheets for asbestos and old paint for lead before removing
  • Disturbing asbestos
  • Lead paint dust and fumes
Extreme
  • Before work, check the asbestos register (workplaces built before 2004). For homes, or if there is no register, have a competent person identify asbestos or assume it is present. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Engineering
  • Friable asbestos (Class A) and more than 10 square metres of non-friable asbestos (Class B) must be removed by a licensed removalist. Administrative
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Administrative
  • Wear a fitted P2 (or better) respirator and disposable coveralls. PPE
  • Test old paint for lead before you sand, scrape, cut or heat it. Eliminate
  • Use wet scraping, chemical strippers or shrouded tools with extraction instead of dry sanding. Never burn off lead paint with an open flame. Substitute
  • Seal off the work area with plastic sheeting and keep residents, children and pets out. Isolate
  • Clean up with an H-class vacuum and wet wipes. Never dry sweep. Engineering
  • Wash hands and face before eating, drinking or smoking. Change out of dusty clothes before going home. Administrative
  • Wear a P2 (or better) respirator, disposable coveralls and gloves. PPE
Medium
3Remove gutters and old fascia boards, lowering them by hand
  • Lifting and carrying heavy loads
  • Falling tools and materials
  • Cuts from sharp edges
High
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Engineering
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Administrative
  • Keep the load close, back straight and no twisting. Turn with your feet. Administrative
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Engineering
  • Use catch fans, debris netting or covered walkways where people pass below. Engineering
  • Tether hand tools when working at height. Engineering
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Administrative
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Engineering
  • Use knives with retractable or self-retracting blades. Engineering
  • Cut away from your body and keep your other hand clear. Administrative
  • Put used blades in a blade bin or sharps container. Administrative
  • Use two people to handle large sheets of metal or glass. Administrative
Medium
4Cut and fix new boards and soffit lining
  • Saw cuts and kickback
  • Nail gun injuries
  • Wood and MDF dust
  • Loud noise
High
  • Keep blade guards fitted and working, and use the riving knife on table saws. Engineering
  • Use push sticks and clamps, and support long pieces so they do not pinch the blade. Engineering
  • Use a sharp, undamaged blade made for the material. Administrative
  • Stand to one side of the blade line, out of the kickback path. Administrative
  • Use a nail gun with a sequential (single shot) trigger, not a contact or bump trigger. Substitute
  • Disconnect the air or battery before clearing jams, adjusting or moving between work areas. Engineering
  • Keep your free hand at least 30 cm from the nailing point. Administrative
  • Never point the gun at anyone or carry it with your finger on the trigger. Administrative
  • Buy pre-cut or pre-finished timber where you can. Substitute
  • Cut outdoors or in a well-ventilated area away from others. Isolate
  • Use saws and sanders with dust extraction connected to an M-class (or better) vacuum. Engineering
  • Clean up with a vacuum, not a broom or compressed air. Administrative
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Engineering
  • Limit time on noisy tools and rotate workers. Administrative
  • Keep exposure below 85 dB(A) over 8 hours. Give hearing tests to workers who often need hearing protection. Administrative
Medium
5Refit gutters, clean up and remove access
  • Poor housekeeping and waste
  • Falling from a ladder
High
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
  • Do not stand on the top three rungs of an extension ladder or the top step of a stepladder. Administrative
  • Check the ladder before each use: feet, rungs, stiles and locks. Administrative
  • Wear non-slip safety boots with clean soles. PPE
  • Falling from a ladder: see step 1 for the full controls Administrative
Medium

PPE

Steel cap bootsSafety glassesWork glovesP2 dust maskHearing protection (earmuffs or plugs)Hi-vis shirt or vestHard hatHalf-face respirator (P2 or P3 filters)OverallsCut-resistant gloves

Plant and equipment

Mobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 mExtension ladderCircular sawNail gunHand tools

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Free SWMS template for fascia and soffit replacement

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for fascia and soffit replacement

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Barricade below and set up a mobile scaffold or secured ladder
  2. Check soffit sheets for asbestos and old paint for lead before removing
  3. Remove gutters and old fascia boards, lowering them by hand
  4. Cut and fix new boards and soffit lining
  5. Refit gutters, clean up and remove access

Hazards to watch on fascia and soffit replacement

The hazards most specific to this job, and the step where each one comes up.

Step 4Nail gun injuriesA nail gun fires by accident, or a nail goes through the timber or ricochets and hits the user or someone nearby.
Step 4Wood and MDF dustSawing and sanding timber, MDF and treated wood makes fine dust that causes asthma, skin problems and some cancers.
Step 2Lead paint dust and fumesPaint on buildings built before 1970 is likely to contain lead, and anything before 1997 may. Sanding, scraping or heating it releases dust or fumes that poison workers and families, especially children.
Step 2Disturbing asbestosBuildings built before 1990 are likely to contain asbestos, and any built before 2004 may. Drilling, cutting or breaking it releases fibres that cause cancer years later.
Step 4Saw cuts and kickbackCircular saws, drop saws and table saws cut fingers and hands or throw material back at the user.
Step 1, 5Falling from a ladderThe ladder slips or tips, or the worker overreaches, and they fall onto a hard surface.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on fascia and soffit replacement: Extreme before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (likely and catastrophic becomes unlikely and major).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work on a roof?
  • Is there a skylight, clear sheet, fibro or other fragile roofing?
  • Will you use a scaffold or mobile tower?
  • Will you use an EWP (scissor lift or boom lift)?
  • Will you cut, grind or drill concrete, brick, stone, tiles or fibre cement?

Licences and legal requirements in Australia

Equipment on this job that needs a licence, ticket or training:

  • Mobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 m

A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.

Rules that apply: WHS Regulation 2011, Part 4.4 Falls; WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 7.2 Lead; WHS Regulation 2011, Part 4.2 Hazardous manual tasks; WHS Regulation 2011, Part 3.2 (falling objects); WHS Regulation 2011, Part 4.1 Noise.

Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for fascia and soffit replacement?

A SWMS is required by law if fascia and soffit replacement includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for fascia and soffit replacement?

Usually Steel cap boots, Safety glasses, Work gloves, P2 dust mask, Hearing protection (earmuffs or plugs), Hi-vis shirt or vest, Hard hat, Half-face respirator (P2 or P3 filters), Overalls, Cut-resistant gloves. The site rules may add more, so check with the principal contractor.