SWMS for roof leak repair
Yes. Roof leak repair usually includes high risk construction work (risk of a person falling more than 2 metres), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from a roof edge, falling through a fragile roof or skylight, disturbing asbestos and electric shock from live wiring.
SWMS example: roof leak repair
This is a complete SWMS for roof leak repair, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check the roof type and condition from the ground, looking for brittle sheets, skylights and asbestos |
| Extreme |
| Medium |
| 2 | Set up a secured ladder and edge protection or a harness and anchor |
| Extreme |
| Medium |
| 3 | Go into the roof space to find the leak, watching for live cables and weak ceiling joists |
| Extreme |
| Medium |
| 4 | Replace cracked tiles, sheets or flashings and seal joints |
| Medium |
| Medium |
| 5 | Use heat for flashings only with a hot work permit and a fire extinguisher at hand |
| Extreme |
| Medium |
| 6 | Clean up debris, check gutters are clear and remove the ladder |
| High |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for roof leak repair
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for roof leak repair
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Edge protection installed and checked before anyone works above 2 m
- Fragile roof areas and skylights covered or barricaded
- Openings, voids and penetrations covered and marked
- Ladder inspected, secured and extending 1 m above the landing
- Asbestos register or survey checked for the work area
- Hot work permit issued, extinguisher at hand, fire watch arranged
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, safety harness and lanyard, work gloves, safety glasses
The safe sequence of work
- Check the roof type and condition from the ground, looking for brittle sheets, skylights and asbestos
- Set up a secured ladder and edge protection or a harness and anchor
- Go into the roof space to find the leak, watching for live cables and weak ceiling joists
- Replace cracked tiles, sheets or flashings and seal joints
- Use heat for flashings only with a hot work permit and a fire extinguisher at hand
- Clean up debris, check gutters are clear and remove the ladder
Hazards to watch on roof leak repair
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone work on a roof?
- Will you use a scaffold or mobile tower?
- Will you use an EWP (scissor lift or boom lift)?
- Will you sand, scrape, cut or heat paint on a building built before 1997?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Risk of a person falling more than 2 metres
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulation 2011, Part 4.4 Falls; WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 4.7 General electrical safety; WHS Regulation 2011, Chapter 7 Hazardous chemicals; AS 1674.1 Safety in welding and allied processes (fire precautions); WHS Regulation 2011, Part 3.2 (falling objects).
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for roof leak repair?
Yes. Roof leak repair usually includes high risk construction work (risk of a person falling more than 2 metres), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for roof leak repair?
Usually Steel cap boots, Safety harness and lanyard, Work gloves, Safety glasses, Sun protection (brim hat, long sleeves, SPF 50+), Hard hat, Half-face respirator (P2 or P3 filters), Overalls, Cut-resistant gloves, Chemical-resistant gloves (nitrile), Safety goggles, Welding gloves, Face shield. The site rules may add more, so check with the principal contractor.