Method statement for mobile tower scaffold

You must assess the risks of mobile tower scaffold and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, scaffold collapse or fall from scaffold, falling tools and materials and lifting and carrying heavy loads.

RAMS example: mobile tower scaffold

This is a complete RAMS for mobile tower scaffold, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Mobile scaffold tower set up and use · Scaffolding · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Check all parts and the ground, and look up for power lines
  • Contact with overhead power lines
  • Scaffold collapse or fall from scaffold
Workers, Plant operators, Public, People belowVery high (15)
  • Ask the distribution network operator (DNO) to turn off, move or insulate the lines before work starts. Eliminate
  • Use non-conductive (fibreglass) ladders near any power lines. Reduce / substitute
  • Mark the safe distance with flags, tape or goal posts and keep all plant and people outside it. Isolate
  • Follow HSE GS6: barriers, goal posts under the lines and a permit for work near them. Control (procedures)
  • Use a dedicated spotter whenever plant moves or raises anything near lines. Control (procedures)
  • Treat all lines as live. If plant touches a line, stay in the cab and keep everyone well away. Control (procedures)
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Scaffold collapse or fall from scaffold: see step 4 for the full controls Control (procedures)
Medium (5)
2Build to the instructions with outriggers and guardrails
  • Scaffold collapse or fall from scaffold
  • Falling from height
Workers, Public, People belowVery high (20)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Scaffold collapse or fall from scaffold: see step 4 for the full controls Control (procedures)
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile tower or MEWP instead of working off a ladder. Control (engineering)
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Control (engineering)
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Control (procedures)
  • Wear a full body harness with a shock-absorbing lanyard, clipped on at all times when using fall arrest. PPE
Medium (5)
3Lock the wheels before climbing, climb only on the inside
  • Scaffold collapse or fall from scaffold
  • Falling from height
Workers, Public, People belowVery high (20)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
  • Do not overload platforms. Know the duty rating and keep material stacks over the standards. Control (procedures)
  • Scaffold collapse or fall from scaffold: see step 4 for the full controls Control (procedures)
  • Falling from height: see step 2 for the full controls Control (procedures)
Medium (5)
4Never move it with anyone or anything on it
  • Scaffold collapse or fall from scaffold
  • Falling tools and materials
Workers, Public, People belowVery high (15)
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
  • Do not overload platforms. Know the duty rating and keep material stacks over the standards. Control (procedures)
  • Never remove ties, braces, guardrails or boards. Only the scaffolder alters the scaffold. Control (procedures)
  • Wear a hard hat and safety boots on and around the scaffold. PPE
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Use catch fans, debris netting or covered walkways where people pass below. Control (engineering)
  • Tether hand tools when working at height. Control (engineering)
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Control (procedures)
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Control (procedures)
  • Wear a hard hat anywhere objects could fall. PPE
Medium (8)
5Dismantle in reverse order and store parts
  • Lifting and carrying heavy loads
WorkersHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
Medium (6)

Method statement: sequence of work

  1. Check all parts and the ground, and look up for power lines
  2. Build to the instructions with outriggers and guardrails
  3. Lock the wheels before climbing, climb only on the inside
  4. Never move it with anyone or anything on it
  5. Dismantle in reverse order and store parts

PPE

Safety bootsSafety helmetRigger glovesHi-vis vestSafety glasses

Plant and equipment

Mobile access tower: PASMA certificateHand tools

Permits and plans

Work at height permit

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for mobile tower scaffold

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for mobile tower scaffold

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Check all parts and the ground, and look up for power lines
  2. Build to the instructions with outriggers and guardrails
  3. Lock the wheels before climbing, climb only on the inside
  4. Never move it with anyone or anything on it
  5. Dismantle in reverse order and store parts

Hazards to watch on mobile tower scaffold

The hazards most specific to this job, and the step where each one comes up.

Step 1, 2, 3, 4Scaffold collapse or fall from scaffoldA scaffold that is badly built, overloaded or altered collapses or tips, or a worker falls from an unguarded platform.
Step 1Contact with overhead power linesA ladder, MEWP, crane, tipper or long length of material touches or gets close to an overhead line and electrocutes people.
Step 2, 3Falling from heightA worker falls from any height where a fall could cause injury, such as an edge, platform or opening.
Step 4Falling tools and materialsTools, materials or debris fall from above and hit someone working or walking below.
Step 5Lifting and carrying heavy loadsLifting, carrying, pushing or twisting with heavy or awkward loads strains the back, shoulders or knees.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on mobile tower scaffold: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a MEWP (scissor lift or cherry picker)?
  • Was the building built before 2000?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Mobile access tower: PASMA certificate

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: HSE GS6 Avoiding danger from overhead power lines; Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 10 (falling objects); Manual Handling Operations Regulations 1992.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for mobile tower scaffold?

You must assess the risks of mobile tower scaffold and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for mobile tower scaffold?

Usually Safety boots, Safety helmet, Rigger gloves, Hi-vis vest, Safety glasses. The site rules may add more, so check with the principal contractor.