RAMS for scaffold dismantling
You must assess the risks of scaffold dismantling and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, scaffold collapse or fall from scaffold, road traffic and falling tools and materials.
RAMS example: scaffold dismantling
This is a complete RAMS for scaffold dismantling, with 5 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the scaffold is clear of other trades and materials |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 2 | Set an exclusion zone below |
| Public, Children, Workers, People below | High (12) |
| Medium (8) |
| 3 | Dismantle top down, removing ties only as each lift comes down |
| Workers, Public, People below | Very high (20) |
| Medium (5) |
| 4 | Lower components, never drop them |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 5 | Load the truck safely and clean the area |
| Workers, Road users, Public, Visitors | Very high (15) |
| Medium (5) |
Method statement: sequence of work
- Check the scaffold is clear of other trades and materials
- Set an exclusion zone below
- Dismantle top down, removing ties only as each lift comes down
- Lower components, never drop them
- Load the truck safely and clean the area
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for scaffold dismantling
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for scaffold dismantling
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Scaffold inspected in the last 7 days, tag in date
- Exclusion zone and spotter set up for plant and traffic
- Exclusion zone below the work and public kept out
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, safety helmet, full body harness and lanyard, rigger gloves
The safe sequence of work
- Check the scaffold is clear of other trades and materials
- Set an exclusion zone below
- Dismantle top down, removing ties only as each lift comes down
- Lower components, never drop them
- Load the truck safely and clean the area
Hazards to watch on scaffold dismantling
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a MEWP (scissor lift or cherry picker)?
- Was the building built before 2000?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Work at Height Regulations 2005, regulation 10 (falling objects); CDM Regulations 2015; Work at Height Regulations 2005; Manual Handling Operations Regulations 1992; Safety at Street Works and Road Works Code of Practice (Red Book).
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for scaffold dismantling?
You must assess the risks of scaffold dismantling and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for scaffold dismantling?
Usually Safety boots, Safety helmet, Full body harness and lanyard, Rigger gloves, Hi-vis vest, Safety glasses. The site rules may add more, so check with the principal contractor.