SWMS for wall framing
A SWMS is required by law if wall framing includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from height, falling through a floor opening or void, saw cuts and kickback and wood and MDF dust.
SWMS example: wall framing
This is a complete SWMS for wall framing, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Set up a clean, level cutting area away from walkways |
| Medium |
| Low |
| 2 | Cut studs and plates with guards working, keeping hands clear of the blade |
| High |
| Medium |
| 3 | Nail frames together on the deck, using sequential trigger on nail guns |
| High |
| Medium |
| 4 | Stand frames with enough people and brace them straight away |
| High |
| Medium |
| 5 | Guard slab or floor edges and openings near the work |
| Extreme |
| Medium |
| 6 | Clean up offcuts and nails at the end of each day |
| Medium |
| Low |
PPE
Plant and equipment
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for wall framing
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for wall framing
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Edge protection installed and checked before anyone works above 2 m
- Openings, voids and penetrations covered and marked
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, safety glasses, hearing protection (earmuffs or plugs), work gloves
The safe sequence of work
- Set up a clean, level cutting area away from walkways
- Cut studs and plates with guards working, keeping hands clear of the blade
- Nail frames together on the deck, using sequential trigger on nail guns
- Stand frames with enough people and brace them straight away
- Guard slab or floor edges and openings near the work
- Clean up offcuts and nails at the end of each day
Hazards to watch on wall framing
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you use a scaffold or mobile tower?
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for wall framing?
A SWMS is required by law if wall framing includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for wall framing?
Usually Steel cap boots, Safety glasses, Hearing protection (earmuffs or plugs), Work gloves, Hard hat, P2 dust mask, Safety goggles, Face shield. The site rules may add more, so check with the principal contractor.