JHA for exterior house painting
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for exterior house painting before you start.
A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew, and the crew signs it. The main hazards are falling from height, aerial lift tip-over or crush, scaffold collapse or fall from scaffold and disturbing asbestos.
JHA example: exterior house painting
This is a complete JHA for exterior house painting, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check for power lines and set up barricades under the work |
| High |
| Medium |
| 2 | Set up scaffold, aerial lift or secured ladders on firm ground |
| Critical |
| Medium |
| 3 | Test for lead paint and asbestos sheeting before any prep |
| Critical |
| Medium |
| 4 | Wash down and scrape, keeping water away from power |
| High |
| Low |
| 5 | Paint or spray, watching wind drift |
| High |
| Medium |
| 6 | Clean up, dispose of waste paint properly and remove access |
| Medium |
| Low |
PPE
Plant and equipment
Permits and plans
Emergency
Call 911. Add the nearest hospital, the assembly point and the first aid / cpr person for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this JHA.
Free JHA template for exterior house painting
Word (.docx) and PDF, Letter landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for exterior house painting
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- JHA read, explained and signed by everyone on the job
- Guardrails, nets or fall arrest in place before anyone works at 6 ft or more
- Ladder inspected, secured and extending 3 ft above the landing
- Scaffold inspected by a competent person this shift
- Aerial lift pre-start inspection done and the operator is trained and authorized
- Overhead lines identified and safe distances marked
- Asbestos register or survey checked for the work area
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- Wind and weather checked; stop work limits agreed
- First aid / CPR person, first aid kit and emergency number (911) confirmed
- PPE checked and worn: safety-toe boots (ASTM F2413), safety glasses (ANSI Z87.1), N95 respirator, chemical-resistant gloves
The safe sequence of work
- Check for power lines and set up barricades under the work
- Set up scaffold, aerial lift or secured ladders on firm ground
- Test for lead paint and asbestos sheeting before any prep
- Wash down and scrape, keeping water away from power
- Paint or spray, watching wind drift
- Clean up, dispose of waste paint properly and remove access
Hazards to watch on exterior house painting
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work on a roof?
- Is there a skylight, fiberglass panel or other fragile roofing?
- Will you cut, grind or drill concrete, brick, stone, tile or fiber cement?
- Will you use chemicals, solvents, glues, paints or fuels?
- Will people be living or working in the building while you work?
Licences and legal requirements in United States
Equipment on this job that needs a licence, ticket or training:
- Mobile (rolling) scaffold: Erected under a competent person (29 CFR 1926.451)
- Boom lift (aerial lift): Trained and authorized operator (29 CFR 1926.453, ANSI A92.24 training and familiarization)
OSHA requires employers to find and fix hazards and to train workers on them. A JHA breaks the job into steps, lists the hazards in each step and the controls that protect the crew. General contractors often require one before you start.
Rules that apply: 29 CFR 1926.1408 and 1926.416; 29 CFR 1926.501(c); 29 CFR 1926 Subpart M; 29 CFR 1926 Subpart X; 29 CFR 1926.453 (boom lifts); 1926.452(w) and 1926.454 (scissor lifts); 29 CFR 1926 Subpart L; 40 CFR Part 745 (RRP rule) and 29 CFR 1926.62; 29 CFR 1926.1101 and 40 CFR 61 Subpart M (NESHAP); 29 CFR 1926 Subpart K; 29 CFR 1926.59 Hazard Communication; OSH Act Section 5(a)(1) General Duty Clause; state heat rules where they apply (Cal/OSHA T8 3395, WA WAC 296-62-095, OR OAR 437-002-0156, MD COMAR 09.12.32).
Why JHAs get rejected
General contractors send documents back for these reasons. This example avoids them, but check yours too.
- Generic steps such as "work safely" or "use PPE" with no task-specific hazards or controls.
- No OSHA standards referenced for the hazards that have them, such as fall protection, ladders, scaffolds or silica.
- No competent person named for fall protection, excavation, scaffolds or silica where those hazards exist.
- Equipment listed without inspection requirements, and no training listed for the people using it.
- Respirators listed with no respiratory protection program, medical clearance or fit test.
- Controls rely only on PPE when engineering controls such as guardrails, wet cutting or extraction are feasible.
- No crew sign-off, or no date and revision when the job has changed.
Questions
Do I need a JHA for exterior house painting?
OSHA expects employers to find and control hazards on every job, and many general contractors require a written JHA for exterior house painting before you start.
Who signs the JHA?
The supervisor or competent person who prepared it signs, and every crew member signs to show they were trained on the hazards and controls before the job starts. Many general contractors also sign to accept it.
How long do I keep it?
Keep this JHA on site during the job, and keep it with the training and inspection records for at least 1 year after the job (longer if your state plan or general contractor requires it). OSHA does not set a retention period for JHAs themselves.
What PPE is needed for exterior house painting?
Usually Safety-toe boots (ASTM F2413), Safety glasses (ANSI Z87.1), N95 respirator, Chemical-resistant gloves, Sun protection (sunscreen, hat, long sleeves), Personal fall arrest system (harness), High-visibility safety apparel, ANSI/ISEA 107 Class 2 or 3 (Type R near roadways), Hard hat (ANSI Z89.1), Half-face respirator (P100 cartridges), Coveralls, Work gloves, Face shield (ANSI Z87.1), Hearing protection (earmuffs or plugs), Safety goggles (ANSI Z87.1). The site rules may add more, so check with the general contractor.
More painting JHAs
Related jobs in other trades
Toolbox talks for this job
Blank JHA template: free JHA templates. Also for other countries: Australia (SWMS) · United Kingdom (RAMS) · Canada (FLHA)