SWMS for exterior painting
Yes. Exterior painting usually includes high risk construction work (risk of a person falling more than 2 metres; work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are falling from height, EWP tip-over or crush, scaffold collapse or fall from scaffold and disturbing asbestos.
SWMS example: exterior painting
This is a complete SWMS for exterior painting, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Check for power lines and set up barricades under the work |
| High |
| Medium |
| 2 | Set up scaffold, EWP or secured ladders on firm ground |
| Extreme |
| Medium |
| 3 | Test for lead paint and asbestos sheeting before any prep |
| Extreme |
| Medium |
| 4 | Wash down and scrape, keeping water away from power |
| High |
| Low |
| 5 | Paint or spray, watching wind drift |
| High |
| Medium |
| 6 | Clean up, dispose of waste paint properly and remove access |
| Medium |
| Low |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for exterior painting
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for exterior painting
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Edge protection installed and checked before anyone works above 2 m
- Ladder inspected, secured and extending 1 m above the landing
- Scaffold tagged, with a handover certificate if over 4 m
- Elevating work platform pre-start check done and the operator is ticketed
- Overhead lines identified and safe distances marked
- Asbestos register or survey checked for the work area
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: steel cap boots, safety glasses, P2 dust mask, chemical-resistant gloves (nitrile)
The safe sequence of work
- Check for power lines and set up barricades under the work
- Set up scaffold, EWP or secured ladders on firm ground
- Test for lead paint and asbestos sheeting before any prep
- Wash down and scrape, keeping water away from power
- Paint or spray, watching wind drift
- Clean up, dispose of waste paint properly and remove access
Hazards to watch on exterior painting
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you cut, grind or drill concrete, brick, stone, tiles or fibre cement?
- Will you remove, cut, repair or dispose of an existing engineered stone benchtop?
- Will you use chemicals, solvents, glues, paints or fuels?
Licences and legal requirements in Australia
This task can involve these high risk construction work categories under the WHS Regulations:
- Risk of a person falling more than 2 metres
- Work in an area with movement of powered mobile plant
Equipment on this job that needs a licence, ticket or training:
- Mobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 m
- Boom lift (EWP): HRWL WP for boom-type EWPs with a boom of 11 m or more. Under 11 m: trained and assessed (e.g. EWPA Yellow Card)
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulation 2011, Part 3.2 (falling objects); WHS Regulation 2011, Part 4.4 Falls; WHS Regulation 2011, Part 4.5 High risk work; WHS Regulation 2011, Part 4.4 Falls, Part 5.1 Plant and r.225 (scaffolds); WHS Regulation 2011, Part 7.2 Lead; WHS Regulations, Chapter 8 (Asbestos); WHS Regulation 2011, Part 4.7 and AS/NZS 3012; WHS Regulation 2011, Chapter 7 Hazardous chemicals.
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for exterior painting?
Yes. Exterior painting usually includes high risk construction work (risk of a person falling more than 2 metres; work in an area with movement of powered mobile plant), so a SWMS is required by law before work starts.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for exterior painting?
Usually Steel cap boots, Safety glasses, P2 dust mask, Chemical-resistant gloves (nitrile), Sun protection (brim hat, long sleeves, SPF 50+), Safety harness and lanyard, Hi-vis shirt or vest, Hard hat, Half-face respirator (P2 or P3 filters), Overalls, Work gloves, Face shield, Hearing protection (earmuffs or plugs), Safety goggles. The site rules may add more, so check with the principal contractor.