SWMS for spray painting
A SWMS is required by law if spray painting includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.
It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are flammable liquids and gases, fire and emergencies, hazardous chemicals and eye injuries.
SWMS example: spray painting
This is a complete SWMS for spray painting, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
High risk construction work covered
Job steps, hazards and controls
| # | Job step | Hazards | Risk before | Controls | Risk after |
|---|---|---|---|---|---|
| 1 | Mask off and ventilate the area, and remove ignition sources |
| High |
| Medium |
| 2 | Check hoses and tip guard, and lock the trigger when not spraying |
| Medium |
| Medium |
| 3 | Never point the gun at anyone or put a hand near the tip |
| Medium |
| Low |
| 4 | Spray with a respirator and goggles, keeping others out |
| Medium |
| Medium |
| 5 | Release pressure before cleaning or changing tips |
| Medium |
| Low |
| 6 | Clean the pump and dispose of solvent waste properly |
| High |
| Medium |
PPE
Plant and equipment
Permits and plans
Emergency
Call 000. Add the nearest hospital, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this SWMS.
Free SWMS template for spray painting
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for spray painting
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- SWMS read, explained and signed by everyone on the job
- Isolation, lockout and test for dead done before work starts
- First aider, first aid kit and emergency number (000) confirmed
- PPE checked and worn: half-face respirator (P2 or P3 filters), safety goggles, overalls, chemical-resistant gloves (nitrile)
The safe sequence of work
- Mask off and ventilate the area, and remove ignition sources
- Check hoses and tip guard, and lock the trigger when not spraying
- Never point the gun at anyone or put a hand near the tip
- Spray with a respirator and goggles, keeping others out
- Release pressure before cleaning or changing tips
- Clean the pump and dispose of solvent waste properly
Hazards to watch on spray painting
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work more than 2 metres off the ground?
- Will anyone use a ladder or stepladder?
- Will anyone work on a roof?
- Is there a skylight, clear sheet, fibro or other fragile roofing?
- Will you use a scaffold or mobile tower?
Licences and legal requirements in Australia
Equipment on this job that needs a licence, ticket or training:
- Mobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 m
- Scissor lift (EWP): Trained and assessed for the EWP type (e.g. EWPA Yellow Card)
A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.
Rules that apply: WHS Regulation 2011, Chapter 7 Hazardous chemicals; WHS Regulation 2011, regulation 43 (emergency plans).
Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.
Why SWMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
- The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
- Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
- Workers will clip on to a harness but there is no rescue plan for someone left hanging.
- The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
- No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
- Licence or White Card details are missing for workers operating plant or doing licensed high risk work.
Questions
Do I need a SWMS for spray painting?
A SWMS is required by law if spray painting includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.
Who signs the SWMS?
The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.
How long do I keep it?
Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.
What PPE is needed for spray painting?
Usually Half-face respirator (P2 or P3 filters), Safety goggles, Overalls, Chemical-resistant gloves (nitrile), Steel cap boots, Safety glasses, Work gloves, Cut-resistant gloves, Face shield. The site rules may add more, so check with the principal contractor.