SWMS for spray painting

A SWMS is required by law if spray painting includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

It must list the hazards, the controls and how they will be put in place, monitored and reviewed, and the workers must be consulted and sign before starting. The main hazards are flammable liquids and gases, fire and emergencies, hazardous chemicals and eye injuries.

SWMS example: spray painting

This is a complete SWMS for spray painting, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Safe Work Method Statement (SWMS)
Airless spray painting · Painting · Example
Document SWMS-001 · Rev 1

High risk construction work covered

None for this task on its own. Tick any that apply on your site.

Job steps, hazards and controls

#Job stepHazardsRisk beforeControlsRisk after
1Mask off and ventilate the area, and remove ignition sources
  • Flammable liquids and gases
  • Fire and emergencies
High
  • Use non-flammable or water-based products where you can. Substitute
  • Keep ignition sources away: no smoking, no hot work and no running engines near flammables. Isolate
  • Store fuels and solvents in approved, closed containers in a ventilated area away from the work. Engineering
  • Refuel equipment outdoors with the engine off and cool. Administrative
  • Keep only what you need for the day on site. Administrative
  • Store gas cylinders upright, secured and outdoors. Administrative
  • Keep a suitable fire extinguisher where flammables are used or stored. Administrative
  • Wear chemical gloves and safety glasses when pouring or mixing. PPE
  • Provide fire extinguishers suited to the site, checked and easy to reach. Engineering
  • Keep exits and escape routes clear and signed. Engineering
  • Have a site emergency plan: alarm, exits, assembly point and emergency contacts. Administrative
  • Keep a stocked first aid kit and at least one trained first aider on site. Administrative
  • Know the site address and how emergency services get in. Call 000. Administrative
  • Go through the emergency plan with every worker and visitor at induction. Administrative
  • Keep flammable materials and rubbish away from exits and escape routes. Administrative
Medium
2Check hoses and tip guard, and lock the trigger when not spraying
  • Stored energy
  • Hazardous chemicals
Medium
  • Release or block all stored energy before work: release the pressure in pipes, tanks and hoses, bleed hydraulics, release springs, lower loads. Eliminate
  • Lock out and tag all energy sources with personal locks. Isolate
  • Stored energy: see step 5 for the full controls Administrative
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Hazardous chemicals: see step 4 for the full controls Administrative
Medium
3Never point the gun at anyone or put a hand near the tip
  • Stored energy
  • Cuts from sharp edges
Medium
  • Put mechanical blocks or props under raised parts like buckets, tipper bodies and doors. Engineering
  • Test that the system is dead and nothing can move before you start. Administrative
  • Stored energy: see step 5 for the full controls Administrative
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Engineering
  • Use knives with retractable or self-retracting blades. Engineering
  • Cut away from your body and keep your other hand clear. Administrative
  • Put used blades in a blade bin or sharps container. Administrative
  • Use two people to handle large sheets of metal or glass. Administrative
  • Wear cut-resistant gloves and long sleeves. PPE
Low
4Spray with a respirator and goggles, keeping others out
  • Hazardous chemicals
  • Eye injuries
Medium
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Engineering
  • Read the Safety Data Sheet (SDS) before use and keep a register of hazardous chemicals on site. Administrative
  • Keep chemicals in labelled containers. Never decant into drink bottles. Administrative
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Administrative
  • Have eye wash and a spill kit nearby, and wash hands before eating. Administrative
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
  • Use tool guards and screens to stop flying particles. Engineering
  • Use dust extraction and water to keep dust out of the air. Engineering
  • Keep others out of the area when cutting, grinding or chipping. Administrative
  • Keep an eye wash station or eye wash bottles on site. Administrative
  • Wear safety glasses at all times, goggles for dust and chemicals, and a face shield for grinding. PPE
Medium
5Release pressure before cleaning or changing tips
  • Stored energy
Medium
  • Release or block all stored energy before work: release the pressure in pipes, tanks and hoses, bleed hydraulics, release springs, lower loads. Eliminate
  • Lock out and tag all energy sources with personal locks. Isolate
  • Put mechanical blocks or props under raised parts like buckets, tipper bodies and doors. Engineering
  • Test that the system is dead and nothing can move before you start. Administrative
  • Follow the maker's procedure, for example for garage door and roller door springs. Administrative
  • Wear safety glasses and gloves. PPE
Low
6Clean the pump and dispose of solvent waste properly
  • Flammable liquids and gases
  • Poor housekeeping and waste
High
  • Flammable liquids and gases: see step 1 for the full controls Administrative
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skip bins and waste chutes close to the work. Engineering
  • Clean as you go, and do a full clean up at the end of each day. Administrative
  • Keep exits, stairs and walkways clear at all times. Administrative
  • Stack materials neatly on level ground, away from edges. Administrative
  • Wear gloves when handling waste. PPE
Medium

PPE

Half-face respirator (P2 or P3 filters)Safety gogglesOverallsChemical-resistant gloves (nitrile)Steel cap bootsSafety glassesWork glovesCut-resistant glovesFace shield

Plant and equipment

Airless paint sprayerAir compressorMobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 mScissor lift (EWP): Trained and assessed for the EWP type (e.g. EWPA Yellow Card)

Permits and plans

Electrical isolation permit

Emergency

Call 000. Add the nearest hospital, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this SWMS.

Free SWMS template for spray painting

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this SWMS

Pre-start checklist for spray painting

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Mask off and ventilate the area, and remove ignition sources
  2. Check hoses and tip guard, and lock the trigger when not spraying
  3. Never point the gun at anyone or put a hand near the tip
  4. Spray with a respirator and goggles, keeping others out
  5. Release pressure before cleaning or changing tips
  6. Clean the pump and dispose of solvent waste properly

Hazards to watch on spray painting

The hazards most specific to this job, and the step where each one comes up.

Step 1, 6Flammable liquids and gasesPetrol, solvents, thinners and LPG catch fire or explode when vapour reaches a spark, flame or hot surface.
Step 1Fire and emergenciesA fire, injury or other emergency happens and workers cannot get out, raise the alarm or get first aid in time.
Step 2, 3, 5Stored energyEnergy left in springs, hydraulics, compressed gas, raised loads or capacitors releases suddenly and crushes or injures workers.
Step 4Eye injuriesFlying chips, dust, chemicals or sparks get into the eye and cause damage or blindness.
Step 2, 4Hazardous chemicalsGlues, sealants, solvents, acids, cleaners and cement burn skin and eyes or cause breathing problems and poisoning.
Step 3Cuts from sharp edgesSheet metal, glass, blades, cable tray and offcuts cut hands and arms.
Almost certainLikelyPossibleUnlikelyRareHow bad it could be: Insignificant to CatastrophicBA
Highest risk on spray painting: High before controls (B), down to Medium after controls (A), on the Australia 5 by 5 risk matrix (unlikely and catastrophic becomes unlikely and moderate).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work more than 2 metres off the ground?
  • Will anyone use a ladder or stepladder?
  • Will anyone work on a roof?
  • Is there a skylight, clear sheet, fibro or other fragile roofing?
  • Will you use a scaffold or mobile tower?

Licences and legal requirements in Australia

Equipment on this job that needs a licence, ticket or training:

  • Mobile scaffold: Scaffolding HRWL (SB or higher) to erect, alter or dismantle where a person or object could fall more than 4 m
  • Scissor lift (EWP): Trained and assessed for the EWP type (e.g. EWPA Yellow Card)

A SWMS must be prepared before any high risk construction work starts. It must list the high risk work, the hazards and risks, the control measures, and how those controls will be put in place, monitored and reviewed. It must be easy for the workers to read and understand.

Rules that apply: WHS Regulation 2011, Chapter 7 Hazardous chemicals; WHS Regulation 2011, regulation 43 (emergency plans).

Each state has its own regulator and some extra rules: New South Wales, Victoria, Queensland, Western Australia, South Australia and Australian Capital Territory.

Why SWMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • It is generic: another site address, tasks that are not on this job, or no sign it was reviewed for this site. WorkSafe WA says a generic SWMS may not meet the regulations unless it is reviewed and amended for the workplace.
  • The HRCW boxes are not ticked, or the ticks do not match the tasks (for example a roof job with no falls box ticked).
  • Falls are controlled only by "be careful", training or a harness, with no edge protection or scaffold and no reason why higher controls are not reasonably practicable.
  • Workers will clip on to a harness but there is no rescue plan for someone left hanging.
  • The "how controls are implemented, monitored and reviewed" part is missing, or it says the same thing on every row.
  • No worker sign-on, no person responsible for compliance, or a date given to the principal contractor that is before they actually received it.
  • Licence or White Card details are missing for workers operating plant or doing licensed high risk work.

Questions

Do I need a SWMS for spray painting?

A SWMS is required by law if spray painting includes any high risk construction work, such as working where someone could fall more than 2 metres. Many principal contractors ask for one either way.

Who signs the SWMS?

The person conducting the business (PCBU) or their supervisor prepares it with the workers, and every worker doing the high risk work signs to show they were consulted and understand it. Give a copy to the principal contractor before work starts.

How long do I keep it?

Keep this SWMS, and every revised version, until the high risk construction work is finished, where workers and inspectors can see it on site. If a notifiable incident happens during the work, keep it for at least 2 years after the incident.

What PPE is needed for spray painting?

Usually Half-face respirator (P2 or P3 filters), Safety goggles, Overalls, Chemical-resistant gloves (nitrile), Steel cap boots, Safety glasses, Work gloves, Cut-resistant gloves, Face shield. The site rules may add more, so check with the principal contractor.