Method statement for metal roof sheeting

You must assess the risks of metal roof sheeting and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, falling from height, scaffold collapse or fall from scaffold and being hit by mobile plant.

RAMS example: metal roof sheeting

This is a complete RAMS for metal roof sheeting, with 7 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Install metal roof sheets · Roofing · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Install scaffold edge protection and safety mesh before any sheets go up
  • Falling from a roof edge
  • Falling from height
  • Scaffold collapse or fall from scaffold
Workers, People below, PublicVery high (20)
  • Do what you can from the ground or from a scaffold at the gutter line, for example pre-assemble parts on the ground. Eliminate
  • Install edge protection or guardrails on all open roof edges before work starts. Isolate
  • Use a perimeter scaffold with handrails and toe boards along the eaves where practical. Control (engineering)
  • Where guardrails cannot be fitted, use fall restraint on certified roof anchors so workers cannot reach the edge. Control (engineering)
  • Use one safe, controlled access point and keep others off the roof. Control (procedures)
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile tower or MEWP instead of working off a ladder. Control (engineering)
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Control (engineering)
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Control (procedures)
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
  • Do not overload platforms. Know the duty rating and keep material stacks over the standards. Control (procedures)
Medium (5)
2Check wind speed and stop lifting or laying sheets in strong wind
  • Strong wind and storms
Workers, PublicHigh (12)
  • Check the forecast each morning and plan work at height and lifting around the weather. Eliminate
  • Tie down or weigh down loose sheets, panels, boards and rubbish at the end of each shift. Control (engineering)
  • Set wind limits for roof work, platforms and cranes, using the manufacturer's limits, and stop when they are reached. Control (procedures)
  • Stop work and get down in lightning. Wait 30 minutes after the last thunder before going back up. Control (procedures)
  • Check scaffold, fencing and edge protection after strong wind before anyone uses them. Control (procedures)
  • Do not carry large sheets on roofs in wind. Control (procedures)
  • Wear a hard hat with a chin strap at height in windy conditions. PPE
Low (4)
3Lift sheet packs onto the roof with a crane or telehandler, keeping everyone out from under the load
  • Crane and lifting failure
  • Falling tools and materials
  • Contact with overhead power lines
  • Being hit by mobile plant
Workers, Public, People below, Plant operators, VisitorsVery high (15)
  • Barricade the lift zone and keep everyone out from under the load. Isolate
  • Use a crane rated for the load at the radius, set up on firm ground with outrigger pads. Control (engineering)
  • Check slings, chains, shackles and hooks before use. Remove anything damaged or not tagged. Control (engineering)
  • Have a lift plan made by an appointed person, following LOLER. Control (procedures)
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Use catch fans, debris netting or covered walkways where people pass below. Control (engineering)
  • Tether hand tools when working at height. Control (engineering)
  • Ask the distribution network operator (DNO) to turn off, move or insulate the lines before work starts. Eliminate
  • Use non-conductive (fibreglass) ladders near any power lines. Reduce / substitute
  • Mark the safe distance with flags, tape or goal posts and keep all plant and people outside it. Isolate
  • Follow HSE GS6: barriers, goal posts under the lines and a permit for work near them. Control (procedures)
  • Use a dedicated spotter whenever plant moves or raises anything near lines. Control (procedures)
  • Separate people and plant with barriers, exclusion zones and marked walkways. Isolate
  • Use plant with working reversing alarms, cameras and lights. Control (engineering)
  • Have a traffic management plan showing plant routes, loading areas and pedestrian paths. Control (procedures)
  • Use a spotter when reversing or working near people. Control (procedures)
Medium (8)
4Lay sheets one at a time and fix them down straight away so they cannot blow off
  • Lifting and carrying heavy loads
  • Cuts from sharp edges
  • Strong wind and storms
Workers, PublicHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
  • Strong wind and storms: see step 2 for the full controls Control (procedures)
Medium (6)
5Cut sheets with nibblers or shears rather than a grinder where possible
  • Angle grinder injuries
  • Fire from hot works
  • Eye injuries
  • Loud noise
Workers, People nearby, Occupants, PublicVery high (15)
  • Use a guarded saw or a different tool where you can. Reduce / substitute
  • Keep the guard on and use the side handle. Never remove the guard. Control (engineering)
  • Use the right disc for the job, rated for the grinder's speed. Check it for cracks first. Control (procedures)
  • Only trained people change discs, with the grinder unplugged or the battery out. Control (procedures)
  • Use cold work methods where you can, such as bolting, press fittings or cutting with a saw instead of a torch. Eliminate
  • Move anything that can burn at least 10 metres away, or cover it with fire blankets. Isolate
  • Use fire-resistant screens to stop sparks reaching people or gaps in walls and floors. Control (engineering)
  • Get a hot work permit before starting. Control (procedures)
  • Use tool guards and screens to stop flying particles. Control (engineering)
  • Use dust extraction and water to keep dust out of the air. Control (engineering)
  • Keep others out of the area when cutting, grinding or chipping. Control (procedures)
  • Keep an eye wash station or eye wash bottles on site. Control (procedures)
  • Use quieter tools and methods, such as cut-to-size materials, low-noise machines and battery tools. Reduce / substitute
  • Keep noisy plant away from work areas, and use screens or distance between the noise and people. Isolate
  • Keep tools maintained and use mufflers on compressors and generators. Control (engineering)
  • Limit time on noisy tools and rotate workers. Control (procedures)
  • Assess noise. At 85 dB(A) or more, hearing protection is required and the zone must be marked. Control (procedures)
Medium (8)
6Screw off sheets and fit flashings and ridge capping
  • Injury from power tools
  • Heat stress
  • Sun exposure (UV)
  • Burns from hot surfaces
Workers, People nearbyHigh (12)
  • Keep all guards fitted and working. Never tie back or remove a guard. Control (engineering)
  • Clamp or secure the work piece. Do not hold it by hand. Control (engineering)
  • Only trained, competent people use power tools, following the maker's instructions. Control (procedures)
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Control (procedures)
  • Schedule heavy work for the cooler part of the day. Eliminate
  • Provide shade over work and rest areas, and fans or cooling in roof spaces. Control (engineering)
  • Supply cool drinking water close by and drink a cup every 15 to 20 minutes. Control (procedures)
  • Take regular rest breaks in the shade, more often as it gets hotter. Control (procedures)
  • Plan outdoor work for early morning or late afternoon when UV is lower. Eliminate
  • Put shade covers over fixed work areas. Control (engineering)
  • Check the UV index each day. Use sun protection when it is 3 or higher. Control (procedures)
  • Check your skin regularly and see a doctor about any new or changing spots. Control (procedures)
  • Isolate heating systems and let parts cool before you touch them. Eliminate
  • Fit guards or insulation on hot pipes and equipment. Control (engineering)
  • Mark hot items with chalk or a "HOT" sign so others know. Control (procedures)
  • Keep a first aid kit and cool running water nearby for burns. Control (procedures)
Medium (8)
7Sweep off swarf and offcuts, then remove mesh and edge protection last
  • Poor housekeeping and waste
  • Falling from a roof edge
  • Falling tools and materials
Workers, Visitors, People below, PublicVery high (20)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Stop roof work in strong wind or rain, and when the roof is wet, icy or covered in dust or frost. Control (procedures)
  • Wear a harness clipped to a rated anchor when using restraint or fall arrest, and soft-soled non-slip boots. PPE
  • Falling from a roof edge: see step 1 for the full controls Control (procedures)
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Control (procedures)
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Control (procedures)
  • Wear a hard hat anywhere objects could fall. PPE
  • Falling tools and materials: see step 3 for the full controls Control (procedures)
Medium (8)

Method statement: sequence of work

  1. Install scaffold edge protection and safety mesh before any sheets go up
  2. Check wind speed and stop lifting or laying sheets in strong wind
  3. Lift sheet packs onto the roof with a crane or telehandler, keeping everyone out from under the load
  4. Lay sheets one at a time and fix them down straight away so they cannot blow off
  5. Cut sheets with nibblers or shears rather than a grinder where possible
  6. Screw off sheets and fit flashings and ridge capping
  7. Sweep off swarf and offcuts, then remove mesh and edge protection last

PPE

Safety bootsFull body harness and lanyardCut-resistant glovesSafety glassesEar defendersSun protection (sunscreen and neck cover)Safety helmetHi-vis vestRigger glovesFace shieldWelding gauntletsCoverallsSafety goggles

Plant and equipment

Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantleTelehandler: CPCS or NPORS telehandler cardMobile crane: CPCS or NPORS crane operator card, plus slinger signaller card; lift plan by an Appointed PersonPower drillAngle grinder (disc cutter)Hand tools

Permits and plans

Roof access permitWork at height permitLift plan (LOLER reg 8)Hot works permit (fire watch at least 60 minutes after)

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for metal roof sheeting

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for metal roof sheeting

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Install scaffold edge protection and safety mesh before any sheets go up
  2. Check wind speed and stop lifting or laying sheets in strong wind
  3. Lift sheet packs onto the roof with a crane or telehandler, keeping everyone out from under the load
  4. Lay sheets one at a time and fix them down straight away so they cannot blow off
  5. Cut sheets with nibblers or shears rather than a grinder where possible
  6. Screw off sheets and fit flashings and ridge capping
  7. Sweep off swarf and offcuts, then remove mesh and edge protection last

Hazards to watch on metal roof sheeting

The hazards most specific to this job, and the step where each one comes up.

Step 6Burns from hot surfacesTouching hot pipes, tools, bitumen, solder or freshly welded metal burns the skin.
Step 3Crane and lifting failureA load falls or swings, or the crane tips, crushing workers under or near the lift.
Step 5Angle grinder injuriesThe disc shatters, binds or kicks back, causing deep cuts to legs and hands or eye injuries.
Step 1Scaffold collapse or fall from scaffoldA scaffold that is badly built, overloaded or altered collapses or tips, or a worker falls from an unguarded platform.
Step 6Sun exposure (UV)Long hours in the sun cause sunburn, eye damage and skin cancer.
Step 3Contact with overhead power linesA ladder, MEWP, crane, tipper or long length of material touches or gets close to an overhead line and electrocutes people.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on metal roof sheeting: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone use a ladder or stepladder?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you use a MEWP (scissor lift or cherry picker)?
  • Was the building built before 2000?
  • Will you sand, scrape, burn off or cut old paint in a building from before 1992?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle
  • Telehandler: CPCS or NPORS telehandler card
  • Mobile crane: CPCS or NPORS crane operator card, plus slinger signaller card; lift plan by an Appointed Person

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: Work at Height Regulations 2005; Lifting Operations and Lifting Equipment Regulations 1998 (LOLER); Work at Height Regulations 2005, regulation 10 (falling objects); HSE GS6 Avoiding danger from overhead power lines; CDM Regulations 2015 and PUWER 1998; Manual Handling Operations Regulations 1992; CDM 2015 regs 29 to 31 (fire on construction sites). Occupied premises: Regulatory Reform (Fire Safety) Order 2005 (England and Wales), Fire (Scotland) Act 2005, Fire Safety Regulations (NI) 2010; Control of Noise at Work Regulations 2005; Provision and Use of Work Equipment Regulations 1998 (PUWER).

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for metal roof sheeting?

You must assess the risks of metal roof sheeting and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for metal roof sheeting?

Usually Safety boots, Full body harness and lanyard, Cut-resistant gloves, Safety glasses, Ear defenders, Sun protection (sunscreen and neck cover), Safety helmet, Hi-vis vest, Rigger gloves, Face shield, Welding gauntlets, Coveralls, Safety goggles. The site rules may add more, so check with the principal contractor.