Method statement for roof tile replacement
You must assess the risks of roof tile replacement and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, falling from height, silica dust from concrete, brick, stone and tiles and scaffold collapse or fall from scaffold.
RAMS example: roof tile replacement
This is a complete RAMS for roof tile replacement, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Check the weather, look for overhead power lines and barricade the area below the work |
| Workers, Public, Plant operators, Children, People below | High (12) |
| Medium (8) |
| 2 | Set up scaffold or roof edge protection and a secured ladder for roof access |
| Workers, People below, Public | Very high (20) |
| Medium (8) |
| 3 | Check for brittle or cracked tiles, skylights and roof sheets from the access point, and plan a walking route |
| Workers, People below | Very high (15) |
| Medium (5) |
| 4 | Walk on the tile laps only, clipped to an anchor where there is no edge protection |
| Workers, People below, Visitors, Public | Very high (20) |
| Medium (5) |
| 5 | Lift out broken tiles and stack them or lower them down; never throw them off the roof |
| Workers, Public, People below | High (12) |
| Medium (8) |
| 6 | Cut tiles with a grinder fitted with water or dust extraction, wearing a dust mask and glasses |
| Workers, People nearby | Very high (20) |
| Medium (8) |
| 7 | Fit new tiles, then re-bed and re-point ridge capping, taking breaks in heat and sun |
| Workers | High (12) |
| Medium (8) |
| 8 | Check the roof for tiles cracked during the work, then clear offcuts and loose tiles from the roof and gutters |
| Workers, People below, Visitors, Public | Very high (15) |
| Medium (8) |
| 9 | Take down access equipment last and leave the area below clean for the client |
| Workers, Visitors | High (12) |
| Medium (8) |
Method statement: sequence of work
- Check the weather, look for overhead power lines and barricade the area below the work
- Set up scaffold or roof edge protection and a secured ladder for roof access
- Check for brittle or cracked tiles, skylights and roof sheets from the access point, and plan a walking route
- Walk on the tile laps only, clipped to an anchor where there is no edge protection
- Lift out broken tiles and stack them or lower them down; never throw them off the roof
- Cut tiles with a grinder fitted with water or dust extraction, wearing a dust mask and glasses
- Fit new tiles, then re-bed and re-point ridge capping, taking breaks in heat and sun
- Check the roof for tiles cracked during the work, then clear offcuts and loose tiles from the roof and gutters
- Take down access equipment last and leave the area below clean for the client
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for roof tile replacement
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for roof tile replacement
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Fragile roof areas and skylights covered or barricaded
- Ladder inspected, secured and extending 1 m above the landing
- Scaffold inspected in the last 7 days, tag in date
- Overhead lines identified and safe distances marked
- Water suppression or on-tool extraction fitted; respirators fit tested
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- Wind and weather checked; stop work limits agreed
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, full body harness and lanyard, rigger gloves, safety glasses
The safe sequence of work
- Check the weather, look for overhead power lines and barricade the area below the work
- Set up scaffold or roof edge protection and a secured ladder for roof access
- Check for brittle or cracked tiles, skylights and roof sheets from the access point, and plan a walking route
- Walk on the tile laps only, clipped to an anchor where there is no edge protection
- Lift out broken tiles and stack them or lower them down; never throw them off the roof
- Cut tiles with a grinder fitted with water or dust extraction, wearing a dust mask and glasses
- Fit new tiles, then re-bed and re-point ridge capping, taking breaks in heat and sun
- Check the roof for tiles cracked during the work, then clear offcuts and loose tiles from the roof and gutters
- Take down access equipment last and leave the area below clean for the client
Hazards to watch on roof tile replacement
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will you use a MEWP (scissor lift or cherry picker)?
- Was the building built before 2000?
- Will you sand, scrape, burn off or cut old paint in a building from before 1992?
- Will you use chemicals, solvents, glues, paints or fuels?
- Will people be living or working in the building while you work?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Tube and fitting or system scaffold: CISRS scaffolder card to erect, alter or dismantle
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: HSE GS6 Avoiding danger from overhead power lines; CDM Regulations 2015; Work at Height Regulations 2005, regulation 10 (falling objects); Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 9 (fragile surfaces); Manual Handling Operations Regulations 1992; COSHH Regulations 2002; Control of Noise at Work Regulations 2005.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for roof tile replacement?
You must assess the risks of roof tile replacement and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for roof tile replacement?
Usually Safety boots, Full body harness and lanyard, Rigger gloves, Safety glasses, Sun protection (sunscreen and neck cover), FFP3 dust mask, Safety helmet, Hi-vis vest, Cut-resistant gloves, Face shield, Ear defenders, Half-mask respirator (P3 filters), Safety goggles, Chemical-resistant gloves, Knee pads. The site rules may add more, so check with the principal contractor.