Method statement for gutter replacement

You must assess the risks of gutter replacement and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from height, disturbing asbestos, MEWP tip-over or crush and scaffold collapse or fall from scaffold.

RAMS example: gutter replacement

This is a complete RAMS for gutter replacement, with 9 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.

Risk Assessment and Method Statement (RAMS)
Replace gutters and downpipes · Roofing · Example
Document RAMS-001 · Rev 1

Risk assessment

#ActivityHazardsWho might be harmedRisk beforeControlsRisk after
1Barricade the area below and check for power lines near the gutter line
  • Public entering the work area
  • Contact with overhead power lines
  • Falling tools and materials
Public, Children, Workers, Plant operators, People belowHigh (12)
  • Fence off the site with secure temporary fencing and lock the gates when you leave. Isolate
  • Give pedestrians a safe, marked path around the work, with ramps for prams and wheelchairs. Isolate
  • Use hoarding, covered walkways or catch fans where work is above public areas. Control (engineering)
  • Put signs at each entry: site name, contact number and "No unauthorised entry". Control (procedures)
  • Make the site safe at the end of each day: cover holes, lower plant, remove ladders and lock tools away. Control (procedures)
  • Ask the distribution network operator (DNO) to turn off, move or insulate the lines before work starts. Eliminate
  • Use non-conductive (fibreglass) ladders near any power lines. Reduce / substitute
  • Mark the safe distance with flags, tape or goal posts and keep all plant and people outside it. Isolate
  • Follow HSE GS6: barriers, goal posts under the lines and a permit for work near them. Control (procedures)
  • Use a dedicated spotter whenever plant moves or raises anything near lines. Control (procedures)
  • Treat all lines as live. If plant touches a line, stay in the cab and keep everyone well away. Control (procedures)
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Falling tools and materials: see step 5 for the full controls Control (procedures)
Medium (8)
2Check old gutters, fascia and eaves sheeting for asbestos, and old paint for lead, before cutting
  • Disturbing asbestos
  • Lead paint dust and fumes
Workers, Occupants, Public, Residents, ChildrenVery high (15)
  • Before work on any building built before 2000, check the refurbishment and demolition asbestos survey for the work area (HSE HSG264). If there is none, presume asbestos is present or have it sampled before you start. Eliminate
  • Seal off the work area and keep everyone else out. Isolate
  • If asbestos must be disturbed, keep it wet, use hand tools not power tools, and clean up with an H-class vacuum. Control (engineering)
  • Most asbestos insulation, coatings and insulating board need a licensed contractor. Notifiable non-licensed work is notified to HSE before it starts. Other work needs trained workers and controls. Control (procedures)
  • Stop work straight away if you find suspect asbestos. Do not touch it and tell your supervisor. Control (procedures)
  • Wear a fit-tested FFP3 mask (or better) and disposable type 5 coveralls. PPE
  • Test old paint for lead before you sand, scrape, cut or heat it. Eliminate
  • Use wet scraping, chemical strippers or shrouded tools with extraction instead of dry sanding. Never burn off lead paint with an open flame. Reduce / substitute
  • Seal off the work area with plastic sheeting and keep residents, children and pets out. Isolate
  • Clean up with an H-class vacuum and wet wipes. Never dry sweep. Control (engineering)
  • Wash hands and face before eating, drinking or smoking. Change out of dusty clothes before going home. Control (procedures)
  • Wear an FFP3 mask, disposable coveralls and gloves. PPE
Medium (5)
3Set up a mobile scaffold, MEWP or roof edge protection; use a secured ladder only for short, light work with three points of contact
  • Falling from height
  • Falling from a ladder
  • MEWP tip-over or crush
  • Scaffold collapse or fall from scaffold
Workers, People below, People nearby, PublicVery high (20)
  • Do the work from the ground where you can, for example pre-assemble on the ground or use extension poles. Eliminate
  • Install guardrails or edge protection on all open edges before work starts. Isolate
  • Use a scaffold, mobile tower or MEWP instead of working off a ladder. Control (engineering)
  • Where edge protection is not practical, use a fall restraint or fall arrest system on a rated anchor point. Control (engineering)
  • Use a podium step, mobile tower or MEWP for longer jobs instead of a straight ladder. Reduce / substitute
  • Use EN 131 professional ladders in good condition. Remove any damaged ladder from site. Control (engineering)
  • Set extension ladders at a 4 to 1 angle on firm, level ground, tied or footed, and reaching 1 metre above the landing. Control (engineering)
  • Use ladders only for short, light work (about 30 minutes in one spot). Do not carry heavy or awkward loads up a ladder. Control (procedures)
  • Check the ground before setting up. Use outriggers and spreader pads, and keep clear of trenches, pits and slopes. Control (engineering)
  • Use a platform with tilt alarm and secondary guarding (anti-entrapment) where there is an overhead crush risk. Control (engineering)
  • Use IPAF-trained operators for MEWPs, carrying their PAL card. Control (procedures)
  • Do a pre-start check each day. Keep a trained person on the ground who can lower the platform in an emergency. Control (procedures)
  • Never exceed the safe working load, climb on the rails or use a ladder in the basket. Control (procedures)
  • Scaffold is built, altered and taken down only by CISRS-carded scaffolders, to TG20 or a specific design. Control (engineering)
  • Fit guardrails, mid rails and toe boards on every working platform. Control (engineering)
  • Use mobile scaffolds only on firm, level ground with castors locked and outriggers fitted. Never move one with anyone on it. Control (engineering)
  • Mobile towers are built by PASMA-trained workers. Control (procedures)
  • Inspect the scaffold before first use, after any change or bad weather, and at least every 7 days. Record it on the tag and register. Control (procedures)
Medium (8)
4Clean out the old gutter with gloves on, watching for sharp edges and wasp nests. Wet down any bird or possum droppings and wear a dust mask if there are a lot
  • Cuts from sharp edges
  • Bites and stings
WorkersMedium (9)
  • Deburr or cover sharp edges, and fit edge protectors on exposed sheet metal. Control (engineering)
  • Use knives with retractable or self-retracting blades. Control (engineering)
  • Cut away from your body and keep your other hand clear. Control (procedures)
  • Put used blades in a blade bin or sharps container. Control (procedures)
  • Use two people to handle large sheets of metal or glass. Control (procedures)
  • Wear cut-resistant gloves and long sleeves. PPE
  • Check work areas before starting, and get pest control to remove nests. Eliminate
  • Look before you reach into dark spaces. Control (procedures)
  • Ask owners to keep pets away from the work area. Control (procedures)
  • Know who has allergies and keep their medication, such as an adrenaline auto-injector, close by. Control (procedures)
  • Wear gloves, long sleeves and boots. Use insect repellent outdoors. PPE
Medium (6)
5Cut old gutters into short lengths and lower them down; never drop them
  • Lifting and carrying heavy loads
  • Cuts from sharp edges
  • Falling tools and materials
Workers, Public, People belowHigh (12)
  • Plan to avoid carrying: have materials delivered, and old items picked up, as close as possible to where they are used. Eliminate
  • Use lighter or smaller loads: order smaller bags and shorter lengths, and drain or break down old items before moving them. Reduce / substitute
  • Use trolleys, pallet jacks, hoists, vacuum lifters or plant instead of carrying by hand. Control (engineering)
  • Use a two-person lift for anything heavy, long or awkward. Plan the route first and clear it. Control (procedures)
  • Keep the load close, back straight and no twisting. Turn with your feet. Control (procedures)
  • Cuts from sharp edges: see step 4 for the full controls Control (procedures)
  • Barricade and sign the drop zone under overhead work so nobody walks beneath. Isolate
  • Fit toe boards, kick plates and mesh screens on scaffolds and edges. Control (engineering)
  • Use catch fans, debris netting or covered walkways where people pass below. Control (engineering)
  • Tether hand tools when working at height. Control (engineering)
  • Keep platforms tidy. Do not stack materials near edges or above toe board height. Control (procedures)
Medium (8)
6Check the fascia is sound and replace any rotten sections before fixing brackets
  • Falling from height
  • Injury from power tools
  • Wood and MDF dust
Workers, People below, People nearbyVery high (20)
  • Have a rescue plan so a worker hanging in a harness can be brought down within minutes. Control (procedures)
  • Wear a full body harness with a shock-absorbing lanyard, clipped on at all times when using fall arrest. PPE
  • Falling from height: see step 3 for the full controls Control (procedures)
  • Keep all guards fitted and working. Never tie back or remove a guard. Control (engineering)
  • Clamp or secure the work piece. Do not hold it by hand. Control (engineering)
  • Only trained, competent people use power tools, following the maker's instructions. Control (procedures)
  • Check tools before use. Unplug or remove the battery before changing blades or bits. Control (procedures)
  • No loose clothing, jewellery or long hair near spinning parts. Control (procedures)
  • Buy pre-cut or pre-finished timber where you can. Reduce / substitute
  • Cut outdoors or in a well-ventilated area away from others. Isolate
  • Use saws and sanders with dust extraction connected to an M-class (or better) vacuum. Control (engineering)
  • Clean up with a vacuum, not a broom or compressed air. Control (procedures)
  • Do a COSHH assessment for hardwood and MDF dust. Control (procedures)
  • Wear an FFP3 dust mask for cutting and sanding. PPE
Medium (6)
7Fix brackets to the right fall, then fit the new gutter and downpipes, keeping tools tethered at height
  • Injury from power tools
  • Cuts from sharp edges
  • Falling tools and materials
  • Sun exposure (UV)
Workers, People nearby, Public, People belowHigh (12)
  • Wear safety glasses and hearing protection. Do not wear loose gloves on drills or other rotating tools. PPE
  • Injury from power tools: see step 6 for the full controls Control (procedures)
  • Cuts from sharp edges: see step 4 for the full controls Control (procedures)
  • Lower materials with a hoist, chute or rope. Never throw or drop anything down. Control (procedures)
  • Wear a hard hat anywhere objects could fall. PPE
  • Falling tools and materials: see step 5 for the full controls Control (procedures)
  • Plan outdoor work for early morning or late afternoon when UV is lower. Eliminate
  • Put shade covers over fixed work areas. Control (engineering)
  • Check the UV index each day. Use sun protection when it is 3 or higher. Control (procedures)
  • Check your skin regularly and see a doctor about any new or changing spots. Control (procedures)
Medium (8)
8Seal joints and connect downpipes to the surface water system
  • Hazardous chemicals
  • Lifting and carrying heavy loads
Workers, OccupantsHigh (12)
  • Choose the least harmful product that does the job, for example water-based instead of solvent-based. Reduce / substitute
  • Use chemicals in well-ventilated areas, or use fans and extraction in closed rooms. Control (engineering)
  • Do a COSHH assessment and read the Safety Data Sheet (SDS) before use. Control (procedures)
  • Keep chemicals in labelled containers. Never decant into drink bottles. Control (procedures)
  • Store chemicals away from heat, food and drink, and keep products that react with each other apart. Control (procedures)
  • Have eye wash and a spill kit nearby, and wash hands before eating. Control (procedures)
  • Wear chemical-resistant gloves and safety glasses or goggles as listed on the SDS. PPE
  • Use a respirator with the right cartridge if the SDS calls for one. PPE
  • Rotate tasks and take breaks on long lifting jobs. Control (procedures)
  • Wear gloves for grip and safety boots to protect your feet. PPE
  • Lifting and carrying heavy loads: see step 5 for the full controls Control (procedures)
Medium (6)
9Water test the gutter, clean up swarf and offcuts, and remove access equipment
  • Poor housekeeping and waste
  • Slips and trips
Workers, Visitors, PublicMedium (8)
  • Order materials to size and send packaging back where you can. Eliminate
  • Put skips and waste chutes close to the work. Control (engineering)
  • Clean as you go, and do a full clean up at the end of each day. Control (procedures)
  • Keep exits, stairs and walkways clear at all times. Control (procedures)
  • Stack materials neatly on level ground, away from edges. Control (procedures)
  • Use a registered waste carrier and keep waste transfer notes for at least 2 years. Keep hazardous waste such as asbestos separate, with consignment notes (special waste in Scotland). Control (procedures)
  • Wear gloves when handling waste. PPE
  • Plan walkways and keep them clear of materials, hoses and leads. Eliminate
  • Run leads and hoses overhead on hooks or stands, or along walls, not across walkways. Control (engineering)
  • Fill or cover holes, and lay boards or mats on muddy access paths. Control (engineering)
  • Clean up offcuts, packaging and spills as you go, not at the end of the day. Control (procedures)
  • Keep work areas, stairs and access paths well lit. Control (procedures)
  • Wear safety boots with good grip, laced up. PPE
Low (4)

Method statement: sequence of work

  1. Barricade the area below and check for power lines near the gutter line
  2. Check old gutters, fascia and eaves sheeting for asbestos, and old paint for lead, before cutting
  3. Set up a mobile scaffold, MEWP or roof edge protection; use a secured ladder only for short, light work with three points of contact
  4. Clean out the old gutter with gloves on, watching for sharp edges and wasp nests. Wet down any bird or possum droppings and wear a dust mask if there are a lot
  5. Cut old gutters into short lengths and lower them down; never drop them
  6. Check the fascia is sound and replace any rotten sections before fixing brackets
  7. Fix brackets to the right fall, then fit the new gutter and downpipes, keeping tools tethered at height
  8. Seal joints and connect downpipes to the surface water system
  9. Water test the gutter, clean up swarf and offcuts, and remove access equipment

PPE

Safety bootsCut-resistant glovesSafety glassesSun protection (sunscreen and neck cover)Hi-vis vestSafety helmetHalf-mask respirator (P3 filters)CoverallsRigger glovesFull body harness and lanyardEar defendersFFP3 dust maskChemical-resistant glovesSafety goggles

Plant and equipment

Extension ladderMobile access tower: PASMA certificateScissor lift (MEWP): IPAF PAL card (3a)Hand toolsPower drill

Permits and plans

Work at height permit

Emergency

Call 999. Add the nearest A&E, the assembly point and the first aider for your site.

Sign-off

Supervisor and every worker sign to confirm they have read and understood this RAMS.

Free RAMS template for gutter replacement

Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.

Make yours in 2 minutes

Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.

Start this RAMS

Pre-start checklist for gutter replacement

Tick these off before work starts. They come from the hazards, permits and equipment in this job.

The safe sequence of work

  1. Barricade the area below and check for power lines near the gutter line
  2. Check old gutters, fascia and eaves sheeting for asbestos, and old paint for lead, before cutting
  3. Set up a mobile scaffold, MEWP or roof edge protection; use a secured ladder only for short, light work with three points of contact
  4. Clean out the old gutter with gloves on, watching for sharp edges and wasp nests. Wet down any bird or possum droppings and wear a dust mask if there are a lot
  5. Cut old gutters into short lengths and lower them down; never drop them
  6. Check the fascia is sound and replace any rotten sections before fixing brackets
  7. Fix brackets to the right fall, then fit the new gutter and downpipes, keeping tools tethered at height
  8. Seal joints and connect downpipes to the surface water system
  9. Water test the gutter, clean up swarf and offcuts, and remove access equipment

Hazards to watch on gutter replacement

The hazards most specific to this job, and the step where each one comes up.

Step 4Bites and stingsSpiders, wasps, bees, ticks and dogs bite or sting workers in roof spaces, under floors and in gardens.
Step 6Wood and MDF dustSawing and sanding timber, MDF and treated wood makes fine dust that causes asthma, skin problems and some cancers.
Step 3MEWP tip-over or crushThe platform tips on soft or sloping ground, the worker is crushed against a beam or ceiling, or is thrown out of the basket.
Step 2Lead paint dust and fumesLead paint was common before the 1970s and was used in some buildings until 1992. Sanding, scraping or heating it releases dust or fumes that poison workers and families, especially children.
Step 3Scaffold collapse or fall from scaffoldA scaffold that is badly built, overloaded or altered collapses or tips, or a worker falls from an unguarded platform.
Step 7Sun exposure (UV)Long hours in the sun cause sunburn, eye damage and skin cancer.
Very likelyLikelyPossibleUnlikelyVery unlikelyHow bad it could be: Negligible to FatalBA
Highest risk on gutter replacement: Very high before controls (B), down to Medium after controls (A), on the United Kingdom 5 by 5 risk matrix (likely and fatal becomes unlikely and major injury).

What changes on your site

This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):

  • Will anyone work on a roof?
  • Is there a fragile roof, skylight or clear roof sheet?
  • Will you cut, grind or drill concrete, brick, stone, tiles or fibre cement?
  • Will you use chemicals, solvents, glues, paints or fuels?
  • Will people be living or working in the building while you work?

Licences and legal requirements in United Kingdom

Equipment on this job that needs a licence, ticket or training:

  • Mobile access tower: PASMA certificate
  • Scissor lift (MEWP): IPAF PAL card (3a)

Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.

Rules that apply: CDM Regulations 2015; HSE GS6 Avoiding danger from overhead power lines; Work at Height Regulations 2005, regulation 10 (falling objects); Control of Asbestos Regulations 2012; Control of Lead at Work Regulations 2002; Work at Height Regulations 2005; Work at Height Regulations 2005 and LOLER 1998; Manual Handling Operations Regulations 1992; Provision and Use of Work Equipment Regulations 1998 (PUWER); COSHH Regulations 2002.

Why RAMS get rejected

Principal contractors send documents back for these reasons. This example avoids them, but check yours too.

  • The method statement is only a list of headings that repeats the risk table and never says how the work is done.
  • The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
  • Residual risk is still High after controls with no extra measures or explanation.
  • It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
  • Work on an older building with no reference to an asbestos survey.
  • Plant and access equipment listed with no inspection, thorough examination or competence evidence.
  • No briefing record, no revision history, or no named supervisor.

Questions

Do I need RAMS for gutter replacement?

You must assess the risks of gutter replacement and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.

Who signs the RAMS?

The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.

How long do I keep it?

Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.

What PPE is needed for gutter replacement?

Usually Safety boots, Cut-resistant gloves, Safety glasses, Sun protection (sunscreen and neck cover), Hi-vis vest, Safety helmet, Half-mask respirator (P3 filters), Coveralls, Rigger gloves, Full body harness and lanyard, Ear defenders, FFP3 dust mask, Chemical-resistant gloves, Safety goggles. The site rules may add more, so check with the principal contractor.