Method statement for skylight installation
You must assess the risks of skylight installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
RAMS cover the hazards, who could be harmed and how, the controls and the safe sequence of work, and the crew is briefed and signs. The main hazards are falling from a roof edge, electric shock from live wiring, falling through a floor opening or void and falling from a ladder.
RAMS example: skylight installation
This is a complete RAMS for skylight installation, with 6 job steps. Open it in the builder to add your site, crew and signatures, change anything, and download a PDF. Or download the free Word template below and fill it in by hand.
Risk assessment
| # | Activity | Hazards | Who might be harmed | Risk before | Controls | Risk after |
|---|---|---|---|---|---|---|
| 1 | Set up roof access and edge protection, and protect the room below from falling debris |
| Workers, People below, Public | Very high (20) |
| Medium (8) |
| 2 | Mark out the opening, checking for cables, pipes and roof framing in the ceiling space |
| Workers, Occupants | Very high (15) |
| Medium (8) |
| 3 | Cut the roof and ceiling opening, then cover or guard the hole straight away |
| Workers, Visitors, Occupants | Very high (15) |
| Medium (8) |
| 4 | Fit the skylight frame and flashing, carrying the glass unit with two people |
| Workers, Occupants | High (12) |
| Medium (8) |
| 5 | Install the light shaft and patch the ceiling |
| Workers, Occupants, People nearby | High (12) |
| Medium (8) |
| 6 | Seal and water test, then clean up and remove access |
| Workers, Visitors, Public | Medium (8) |
| Low (4) |
Method statement: sequence of work
- Set up roof access and edge protection, and protect the room below from falling debris
- Mark out the opening, checking for cables, pipes and roof framing in the ceiling space
- Cut the roof and ceiling opening, then cover or guard the hole straight away
- Fit the skylight frame and flashing, carrying the glass unit with two people
- Install the light shaft and patch the ceiling
- Seal and water test, then clean up and remove access
PPE
Plant and equipment
Permits and plans
Emergency
Call 999. Add the nearest A&E, the assembly point and the first aider for your site.
Sign-off
Supervisor and every worker sign to confirm they have read and understood this RAMS.
Free RAMS template for skylight installation
Word (.docx) and PDF, A4 landscape, no email needed. Fill in your site details, then print or send it.
Make yours in 2 minutes
Same document, filled in for your job. Answer a few yes or no questions, the crew signs on the phone, and you send the PDF.
Pre-start checklist for skylight installation
Tick these off before work starts. They come from the hazards, permits and equipment in this job.
- RAMS read, explained and signed by everyone on the job
- Edge protection or fall protection in place before work at height starts
- Openings, voids and penetrations covered and marked
- Ladder inspected, secured and extending 1 m above the landing
- Exclusion zone below the work and public kept out
- Weather checked: water, shade and rest breaks planned
- First aider, first aid kit and emergency number (999) confirmed
- PPE checked and worn: safety boots, full body harness and lanyard, cut-resistant gloves, safety glasses
The safe sequence of work
- Set up roof access and edge protection, and protect the room below from falling debris
- Mark out the opening, checking for cables, pipes and roof framing in the ceiling space
- Cut the roof and ceiling opening, then cover or guard the hole straight away
- Fit the skylight frame and flashing, carrying the glass unit with two people
- Install the light shaft and patch the ceiling
- Seal and water test, then clean up and remove access
Hazards to watch on skylight installation
The hazards most specific to this job, and the step where each one comes up.
What changes on your site
This example covers the job itself. Your site may add more. Add controls for any of these that apply (the builder asks you these as yes or no questions):
- Will anyone work at height, anywhere a fall could hurt them?
- Will anyone work on a roof?
- Is there a fragile roof, skylight or clear roof sheet?
- Will you use a scaffold or mobile tower?
- Will you use a MEWP (scissor lift or cherry picker)?
Licences and legal requirements in United Kingdom
Equipment on this job that needs a licence, ticket or training:
- Mobile access tower: PASMA certificate
Employers must assess the risks of their work and record the significant findings (required where you employ 5 or more people). On CDM projects, contractors give their RAMS to the principal contractor before starting, and brief the workers on it.
Rules that apply: Work at Height Regulations 2005; Work at Height Regulations 2005, regulation 10 (falling objects); Electricity at Work Regulations 1989; Provision and Use of Work Equipment Regulations 1998 (PUWER); Manual Handling Operations Regulations 1992.
Why RAMS get rejected
Principal contractors send documents back for these reasons. This example avoids them, but check yours too.
- The method statement is only a list of headings that repeats the risk table and never says how the work is done.
- The method sequence does not match the risk assessment, for example the method strips the roof before the scaffold is handed over.
- Residual risk is still High after controls with no extra measures or explanation.
- It reads as copied: another firm, another address, or wording that does not fit UK sites. HSE warns that copying an example and adding your name does not satisfy the law.
- Work on an older building with no reference to an asbestos survey.
- Plant and access equipment listed with no inspection, thorough examination or competence evidence.
- No briefing record, no revision history, or no named supervisor.
Questions
Do I need RAMS for skylight installation?
You must assess the risks of skylight installation and record the significant findings if you employ 5 or more people. On CDM sites the principal contractor will ask for RAMS before you start.
Who signs the RAMS?
The person who wrote it and the person who approved it sign and date it. Every worker signs the briefing register after it is explained to them, and the principal contractor reviews and accepts it before you start.
How long do I keep it?
Keep this RAMS, every revision and the signed briefing register with the site file for the length of the job, and keep a copy in your records afterwards.
What PPE is needed for skylight installation?
Usually Safety boots, Full body harness and lanyard, Cut-resistant gloves, Safety glasses, FFP3 dust mask, Sun protection (sunscreen and neck cover), Safety helmet, Ear defenders, Rigger gloves. The site rules may add more, so check with the principal contractor.